New Lehigh Elementary School
• Continued stage rigging and lighting installation in the Gymnasium. • Began installation of all rack mounted equipment. • Began installation of wireless access points throughout the building. • Completed testing and balancing of the HVAC systems. • Completed installation of fire alarm system. • Continued installation of access control devices and implementing programs. • Successfully completed the elevator inspection with L&I. • Completed the testing and inspection of the kitchen fire protection system. Work in Progress - Building (CONT.)
Cafeteria wall finishes are complete, and cleaning is ongoing.
May 2021