New Lehigh Elementary School
Work In Progress
•Phase 2B: Interior finishes, MEP equipment installation and start-up, electrical systems and finishes, contractor clean-up, District move-in •Start: April 15, 2019 •Completion of Phase: June 15, 2021 Phase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.
Work in Progress - Building
• Continued installation of aluminum gutters, downspouts, and roof edging. • Continued painting of interior walls and door frames.
• Continued installation of Owner supplied items. • Installed acoustic sound panels in the cafeteria.
• Began cleaning and sealing floors in the classroomwing. • Completed the wood athletic floor and game lines in the gymnasium. • Completed the installation and testing of kitchen equipment.