• Coordinated site access for furniture deliveries scheduled for early June. • Coordinated the delivery and installation of play equipment. • Completed installation of exterior site lighting for Site Phase 2B. • Began connection of new building to the existing well and septic. • Continued planning for abatement and demolition of the existing building.
• Continued grading and topsoiling around the building. • Installed sod and seed in previously topsoiled areas. • Continued installation of chain link fencing. • Completed framing and roofing of play area pavilion. • Completed concrete curbing. • Maintained E&S controls.
Paint, carpeting, and millwork is complete in the Library.