WCSD New K-1 Elementary School
Animated publication
New K-1 Elementary School Whitehall Coplay School District DEI Project No. 281003 Monthly Progress Report No. 3 July 2022
New K-1 Elementary School Whitehall Coplay S
SITE PHASING PLAN S1-S2: Site Preparation, Complete Structure Demolition, Utility Capping and Relocations
Start: April 2022 Completion: June 2022
• Completion of structure demolition. • Completion of new sanitary storm sewer main from the public library parking lot to future tie-in location of new building system. The tie in of the high school system is complete allowing for the demolition and capping of previous line. • The 8” water main serving the campus was tapped with valves and fittings in preperation for future relocation of line. • Excavation and repair of sinkholes discovered during building demolition is complete. WORK COMPLETED • Earlier than anticipated, delivery of HDPE pipe has allowed for the installation of the temporary and permanent stormwater conveyance systems to begin. • Installation of two temporary sediment traps and rough grading of the entire site. • The relocation of underground communications and power lines along Zephyr Boulevard. • Initial excavation and construction of building pad in preparation for classroom area foundations. • Building Phase B1 ClassroomMasonry Building Construction WORK Commencing
School District
Demolition of DAO slabs and foundations.
Initial excavation of sinkhole discovered under former DAO slab on grade.
July 2022
New K-1 Elementary School Whitehall Coplay S
Demolition of DAO slabs and foundations.
Relocation of power and communication lines.
School District
Installation of storm sewer system EX1-DBE3.
Installation of storm sewer systemMHB1X-MHB8.
July 2022
New K-1 Elementary School Whitehall Coplay S
School District: Whitehall-Coplay School District Project Name: New K-1 Elementary School Project Number: 281003
2022
Overall Project Schedule Status
A M J J A S O N D J-
Site Work Phase 1 Site Work Phase 2 Phase 1 - Building Construction Phase 2 - Core Space Building construction Owner Occupancy / Closeout
2022
Current Phase and Schedule Status
J
A M J J A S O N D
Site Work Phase 1
Install staging and storm water basins Relocate existing underground communications, electric and water lines Demolish and remove existing Admin bldg., barn and other storage bldgs. Site Work Phase 2 Excavate for Building Pad, Import structural fill, rough grade site Install utilities Construct parking areas, driveways, sidewalks and playground Phase 1 - Building Construction Foundations, Slab on grade construction Exterior walls, Roof (Watertight) Interior Partitions, MEP Fixtures and Equipment Phase 2 - Core Space Building Construction Core Space Construction and Finishes
Repairs of sinkholes discovered during building demolition. Stormwater HDPE pipe substitution approved to improve lead times. Pipe was delivered and installation has begun. Issues Resolved
Contract Amount 22,265,000 $
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric Plumbing Contractor: Vision Mechanical ATC Contractor: Johnson Controls
$ $ $ $ $ $
$ $ $ $ $ $ $
3,551,000 3,758,000 1,722,000 687,500 31,983,500 7,959,650 2,000,000
Total Total Soft Costs: Current Remaining Project Contingency
School District
Report Submission Date:
July 2022
Report Author:
Matt McClarin
2023
2024
Status Comments
-F M-A M-J J-A S-O N-D J F M A M J
J
% Complete
10% 35%
2023
2024
Status Comments
J F M A M J
J A S O N D J
% Complete
75%
100% 100% 50%
Installed staging area.
PP&L is scheduled to complete switchover.
Structure demolition is complete
10%
40%
Issues in Progress
Ductile iron pipe lead times for installation of relocated water main.
Paid to Date (with 10% retained)
Original Material Allowance
Remaining Material Allowance
Executed Change Orders
$ $ $ $ $ $
2,570,748
$ $ $ $ $ $
27,730
$ $ $ $ $ $
104,350 396,050 86,135 66,290 687,500
$ $ $ $ $ $
394,648 97,931 86,135 66,290 687,500
67,500 74,700 83,200
7,815
18,705
2,574
-
-
2,796,147
56,823
1,340,325
1,332,504
July 2022
Dr. Robert Steckel, Jr. – Superintendent Christopher Schiffert – Assistant to the Superintendent J. Michael Malay, Jr. – Business Manager Stephen Seier – Director of Educational Operations Phil Bankos – Supervisor of Buildings and Grounds
WCSD Board of Directors William Fonzone, Sr. President George Makhoul, Vice President Patty Gaugler, Member Nichole Hartman, Member Keri Kromer, Member Fady Salloum, Member Allison Schultz, Member Joseph Shields, Member George Williams, Treasurer
Construction Manager – D’Huy Engineering Project Architect – Breslin Architects
Contractors Skepton Construction Inc. General Contractor
JBMMechanical Mechanical Contractor
Wind Gap Electric Inc. Electric Contractor
Vision Mechanical Inc. Plumbing Contractor
Johnson Controls ATC Contractor
Made with FlippingBook Digital Publishing Software