Upper Providence Township New Emergency Service Facility
Report Submission Date: March 2022
Report Author: Michael DePodwin Report Submission Date: November 2021
21
2022
J
A S O N
D J
F M A M J
% Complete
Status Comments
Report Author: Michael DePodwin
Complete
1
2022
100% 100% 99% 99%
Furniture delivery ongoing. Slab on Grade and Structural Steel complete. Exterior walls complete. Roof weathertight. Interior block wall complete. MEP rough‐in ongoing Interior block filler ongoing. Complete Complete Concrete complete. Final landscaping in spring. Base and binder paving courses complete. Fence to be co let d All light pole bas s installed. Light p le ins allation ongoing Complete Stabilization of site complete Base and binder paving courses complete. Complete Soffits and fascia to be completed Complete except for MDP installation. Quartz tile and MEP start up remaining. Punchlist ongoing Status Comments Resubmittals nearing completion Complete
A S O N
D J
F M A M J
% Complete
99%
100% 90% 90%
98% 20% 50%
10% 0% 0%
100% 100% 100%
85% 75%
90% 99%
0% 0%
100
25% 60%
Phase 1 2021
Status Comments
J A S O N D J F M A M J
% Complete 0%
99% 99% 95%
Complete except for MDP installation. Waiting on MDP delivery.
0%
Phase 1 2021
Status Comments
Touch up paint remaining
A S O N D J F M A M J
% Complete
95% Start up remaining
100% 100%
Complete Complete
Quartz tile and apparatus bar floor repair remaining ASI-10 work to be completed 0% Ongoing - to be complete when MDP and gas is active Roof weathertight. Metal roof and cap sheet outstanding. Complete All system installation ongoing. 99% 90% 10%
80%
100%
Underway 95% Nearing completion 80% 10% Block filler underway
Issues in Progress
$ Track "work to complete" and punchlist items and begin closeout and O&M process Determine appropriate action on the urethane cement floor finish system in the Apparatus Bay. Continue to coordinate ASI 11 work with ETI, ETI's controls subcontractor, and UPT's security vendor. Expedite the installation of PECO gas line and delivery of MDP to have permanent power on site. 0% Issues in Progress Review cost proposal from ETI regarding low voltage, security, and access control changes. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Ensure site hours, noise, and lighting are compliant with Township ordinances. Continue to track equipment and material procurement to ensure critical path remain on schedule. Executed Change Orders Original Material Allowance
Paid to Date (with 10% retained)
Remaining Material Allowance
$ $ $ $ $
170,292 47,807 98,883 64,622 381,604
$ $ $ $ $
6,666,187
$ $ $ $ $
- -
389,190 37,920 47,807 94,098 47,807 209,365
989,894
$ $ Original Material Allowance
Paid to Date (with 10% retained)
9,652,926 482,268 1,171,476 825,369
147,752 Executed Change Orders
Remaining Material Allowance
-
$ $
4,818,025
$ $ $ $ $
‐
$ $ $ $ $
209,365
$ $ $ $ $
184,489 47,807 98,883 64,622 395,800
147,752 ‐
533,674 476,034
‐ ‐ ‐
389,190 37,920 94,098
6,310,001
0% Submittals
100% Requests for Information 0% Requests for Information
0%
Approved Rejected Voided Overdue
0%
13%
Complete Outstanding Voided Overdue
0% Submittals
0%
0%
87%
Approved Rejected Voided Overdue
0%
13%
Complete Outstanding Voided Overdue
0%
2%
87%
98%