Construction Manager
New Central Emergency Services Facility Upper Providence Township
DEI Project No.720001 Monthly Progress Report No.05 August 2021
New Central Emergency Services Facility
CURRENT MILESTONES DATES: Complete: P1.1 – P1.10, P1.12, P1.13 Complete building pad (05/28/21) Place building foundations (06/11/21) Install underground water & sanitary (05/11/21) Ongoing: P1.14 – P1.18 Complete under slab MEP (09/07/21) Complete and cure Slab on Grade (09/17/21) Erect Structural Steel (08/04/21) Complete Exterior MasonryWalls (09/03/21)
Site Construction Progress
• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Continue Belgian block and concrete curb installation. • Complete roadway subgrade installation. • Complete underground conduit installation for site lighting. Site Construction Progress
• Continue under slab MEP installation. • Interior masonry wall installation at Areas A and B while coordinating with MEP for in-wall rough-ins nearing completion. • Prep & pour slab-on-grade in Area A. • Structural steel erection and detailing nearing completion. • Complete installation of metal roof decking. • Exterior masonry wall installation starting at the main entrance nearing completion. • Begin mechanical hanger installation and pipe rough-in. • Complete installation of apparatus bay trench drains. • Begin electrical panel and feeder installation. Building Construction Progress
Plumbing rough-in ongoing
y
Concrete slab-on-grade installation ongoing.
August 2021
New Central Emergency Services Facility
Projected Progress for Sept. 2021
• Complete interior masonry wall installation and in-wall electrical rough-ins. • Complete exterior masonry wall installation. • Complete under slab MEP installation including the interior section of the apron
heating system and apparatus bay trench drains. • Complete erection and detailing of structural steel. • Complete all concrete slab pours. • Complete concrete curb installation and road subgrade. • Begin installation of 2-ply membrane roof. • Complete mechanical duct and pipe hanger installation. • Begin overhead MEP rough-in in apparatus bay.
Trench Drain Installation Nearing Completion
Roadway Sub-base ongoing.
y
Mechanical Room Under-slab Conduit Installation Complete.
Perimeter roof blocking ongoing. Metal roof decking complete.
August 2021
Building Layout
Aerial view of building superstructure and material laydown area (August 2021).
Site Overview (August 2021).
August 2021
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
20
Overall Project Schedule Status
J
F M A M J
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals
P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping
P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion
Current Phase and Schedule Status
J F M A M J
P1.8‐P1.11 ‐ Install MEP to building pad P1.14 ‐ Complete under slab MEP piping and conduit P1.15 ‐ Complete Slab on Grade P1.16 ‐ Slab on Grade Curing Time P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls
Issues Resolved Confirm installation detail and construction sequence of the apparatus bay trench drains. Confirmation of Belgian block curb detail, width of main loop road entrance, roof drain cleanout product. Coordinate the FF&E process with GKO and the Township. GKO confirmed building efficiency through a COMCheck stemming from perimeter insulation question.
Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.
Contract Amount
$ $ $ $ $
7,462,000 1,123,000 1,212,400
922,197
Total Total Soft Costs: Current Remaining Project Contingency
10,719,597
Other Discussion
Report Submission Date: August 2021
Report Author: Michael DePodwin
021
2022
J
A S O N
D J
F M A M J
% Complete
Status Comments
Slab on Grade and Structural Steel detailing ongoing Exterior block wall isntallation ongoing Interior block wall and MEP rough‐in ongoing Resubmittals nearing completion
90% 40% 75% 95%
0% 0% 0%
Fence to be completed
50% 90% 99%
Underground rough‐in nearing completion Curbs complete, stone base nearing completion Stabilization of site complete
0% 0% 0% 5%
Phase 1 2021
Status Comments
J A S O N D J F M A M J
% Complete
50% 50% 95% 90%
All utilities have been terminated building side save for gas. Rough‐ins nearing completion Area B slab on grade complete Area A slab on grade ongoing. Erection and detailing nearing completion.
90% Exterior walls nearing completion 90% 5% Roof blocking underway
80% Interior walls ongoing
Issues in Progress
Complete a building low voltage, security, and access control design with GKO and CEI. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Work with Vision Mechanical on resolving sprinkler shops drawings and calculations.
Work with Lobar on roof nailboard and stone veneer procurement.
Paid to Date (with 10% retained)
Original Material Allowance
Remaining Material Allowance
Executed Change Orders
$ $ $ $ $
3,560,815
$ $ $ $ $
‐ ‐ ‐ ‐
$ $ $ $ $
209,365 47,807 94,098 37,920 389,190
$ $ $ $ $
189,198 47,807 92,910 64,622 394,537
129,598 360,850 360,188
4,411,451
‐
1% Submittals
Requests for Information
0%
Approved Rejected Voided Overdue
2% 0%
12%
0%
Complete Outstanding Voided
87%
98%
Printed 9/10/2021
Tim Tieperman – Township Manager Bryan Bortnichak – Assistant Township Manager Dan Kerrigan – Chief of Fire And Emergency Services
Board of Supervisors Bill Starling – Chair Laurie Higgins – Vice Chair
Helene Calci John Pearson Albert Vagnozzi
Construction Manager D’huy Engineering, Inc.
Project Architect Gko Architects, Llc
Civil Engineer Gilmore & Associates, Inc.
Contractors Lobar, Inc. General Construction
Tri-County Mechanical, Inc. Mechanical Construction
Electri-Tech, Inc. Electrical Construction
Vision Mechanical, Inc. Plumbing Construction