Upper Providence Township, New Central Station Emergency Services Township
New Central Emergency Services Facility
CURRENT MILESTONES DATES: Complete: P1.1 – P1.10, P1.12, P1.13 Complete building pad (05/28/21) Place building foundations (06/11/21) Install underground water & sanitary (05/11/21) Ongoing: P1.14 – P1.18 Complete under slab MEP (09/07/21) Complete and cure Slab on Grade (09/17/21) Erect Structural Steel (08/04/21) Complete Exterior MasonryWalls (09/03/21)
Site Construction Progress
• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Continue Belgian block and concrete curb installation. • Complete roadway subgrade installation. • Complete underground conduit installation for site lighting. Site Construction Progress
• Continue under slab MEP installation. • Interior masonry wall installation at Areas A and B while coordinating with MEP for in-wall rough-ins nearing completion. • Prep & pour slab-on-grade in Area A. • Structural steel erection and detailing nearing completion. • Complete installation of metal roof decking. • Exterior masonry wall installation starting at the main entrance nearing completion. • Begin mechanical hanger installation and pipe rough-in. • Complete installation of apparatus bay trench drains. • Begin electrical panel and feeder installation. Building Construction Progress
Plumbing rough-in ongoing