New Lehigh Elementary School
Report Submission Date: December 2020
Report Author: M. Evans
2020
2021
Status Comments
O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D
% Complete
100% 100% 100% 95% 100% 100%
Parking lot utility work completed.
Finalized new parking and service areas. Secure site for school.
Bus driveway base paving and curbing is completed.
10% 30% 75%
Parking lot base tie ‐ in complete. Landscaping behind curbs ongoing.
Relocation/removal of contractor storage boxes.
0% 0% 0% 0% 0% 0%
Phases are scheduled for Sept. 2021 through Jan. 2022
Phase is scheduled for May 2022
Phases are scheduled for August 2022 Phases are scheduled for June ‐ July 2022
Building foundation complete. Storm Tie ‐ ins complete.
100% 100%
Load bearing CMU complete.
Brick veneer complete. Curtain walls and CMP fascia's are ongoing.
95% 98% 85% 75% 80%
Building enclosed. Roof detailing ongoing. MEP equipment installation ongoing.
Wall paint and floor finishes ongoing in Classroom wings.
Substantial Completion 5/27/21.
0%
2022
Status Comments
M J J A S O N D J
F M A M
% Complete
Install and grade subbase, install base paving where available. Ceilings, flooring and casework ongoing in the classroom wing. Exterior concrete paving and rough grading in parking area. Primary power installation by 12/11/2020. Start ‐ ups to follow. Detailing remaining on flat roof, curtain walls installed. Basement mechanical equipment piping is ongoing.
95% 85% 80% 65% 30% 10%
Issues in Progress
Paid to Date (with 10% retained)
Remaining Material Allowance
Executed Change Orders
Original Material Allowance
0 3 6 0 6 0 0 0
$ $ $ $ $ $
3,179,051 1,430,335 2,751,854 16,569,981
$ $ $ $ $ $
138,200
$ $ $ $ $ $
113,400 56,375 53,150 255,625
$ $ $ $ $ $
72,117 43,536 88,337 51,819
‐
(148,314)
‐ ‐
‐
9,350
9,350
23,931,221
(10,114)
487,900
265,158