New Lehigh Elementary School

Report Submission Date: December 2020

Report Author: M. Evans

2020

2021

Status Comments

O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

% Complete

100% 100% 100% 95% 100% 100%

Parking lot utility work completed.

Finalized new parking and service areas. Secure site for school.

Bus driveway base paving and curbing is completed.

10% 30% 75%

Parking lot base tie ‐ in complete. Landscaping behind curbs ongoing.

Relocation/removal of contractor storage boxes.

0% 0% 0% 0% 0% 0%

Phases are scheduled for Sept. 2021 through Jan. 2022

Phase is scheduled for May 2022

Phases are scheduled for August 2022 Phases are scheduled for June ‐ July 2022

Building foundation complete. Storm Tie ‐ ins complete.

100% 100%

Load bearing CMU complete.

Brick veneer complete. Curtain walls and CMP fascia's are ongoing.

95% 98% 85% 75% 80%

Building enclosed. Roof detailing ongoing. MEP equipment installation ongoing.

Wall paint and floor finishes ongoing in Classroom wings.

Substantial Completion 5/27/21.

0%

2022

Status Comments

M J J A S O N D J

F M A M

% Complete

Install and grade subbase, install base paving where available. Ceilings, flooring and casework ongoing in the classroom wing. Exterior concrete paving and rough grading in parking area. Primary power installation by 12/11/2020. Start ‐ ups to follow. Detailing remaining on flat roof, curtain walls installed. Basement mechanical equipment piping is ongoing.

95% 85% 80% 65% 30% 10%

Issues in Progress

Paid to Date (with 10% retained)

Remaining Material Allowance

Executed Change Orders

Original Material Allowance

0 3 6 0 6 0 0 0

$ $ $ $ $ $

3,179,051 1,430,335 2,751,854 16,569,981

$ $ $ $ $ $

138,200

$ $ $ $ $ $

113,400 56,375 53,150 255,625

$ $ $ $ $ $

72,117 43,536 88,337 51,819

(148,314)

‐ ‐

9,350

9,350

23,931,221

(10,114)

487,900

265,158