New Lehigh Elementary School
School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034
2019
Overall Project Schedule Status
J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O
Site Milestones 1S.1 ‐ 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT ‐ 4/30 1S.3 ‐ 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 ‐ 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 ‐ 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 ‐ 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 ‐ 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 ‐ 2BS.8: Topsoil install, painting of lots and drives 3S.1 ‐ 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 ‐ 3S.7: Abatement, installation of access roads and parking lots 4S.1 ‐ 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 ‐ 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 ‐ 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1 ‐ 1B.3 ‐ Prelim prep work, excavation & site, footings & foundations
1B.4 ‐ Load bearing CMU 1B.5 ‐ Exterior wall finishes
1B.6 ‐ 1B.8 ‐ Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9 ‐ 1B.12 ‐ Construction of interior walls, MEP rough ‐ ins and equipment installation 1B.13 ‐ 1B.16 ‐ Interior & floor finishes, equipment start ‐ up & commissioning, exterior finishes.
1B.17 ‐ 1B.19 ‐ Contractor cleanup and punchlist 1B.20 ‐ 1B.21 ‐ District cleanup, setup and move in
2020
2021
D J
F M A
Current Phase and Schedule Status ‐ Site Phase 2B and Building Phase 1
1B.5 ‐ 1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 1B.10 ‐ 1B.12, 1B.15: MEP equipment piping and fixture installations 1B.13 ‐ 1B.14: Ceiling and interior paint, floor finishes, wall coverings and displays installation 2BS.3 ‐ 2BS.8: Construct fire lane, install curbing, sidewalk, new parking lot, begin landscaping 3S.6 ‐ 3S.7: Finalize installation of bus/service access road and main parking area. 1B.15, 1B.17 ‐ 1B.21: Equipment start ‐ up and commissioning,clean ‐ up and punchlist, set ‐ up/move in Issues Resolved RCN and NASD established a plan to maintain network connectivity in both buildings. PPL primary lines have been connected from the utility pole to the pad mounted transformer.
Contract Amount
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.
$ $ $ $ $ $ $ $
5,499,330 1,157,573 29,289,026 4,080,000 1,663,000 3,341,000 118,026 20,087,000
Total Total Soft Costs: Current Remaining Project Contingency:
G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034 updated June 2020.xlsx