New Lehigh Elementary School

Animated publication

Construction Manager

NEW LEHIGH ELEMENTARY SCHOOL Northampton Area School District

DEI Project No.022034 Monthly Progress Report No.20 December 2020

Work In Progress

•Phase 2B: Interior and exterior finishes, MEP equipment installation and start-up, electrical systems and finishes. •Start: April 15, 2019 •Completion of Phase: June 15, 2021 ase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.

• Continued installation of exterior metal fascia and soffits. • Commenced the installation of aluminum gutters and downspouts. • Continued installation of lighting and electrical devices in the classroomwing. • Continued interior painting of walls and door frames throughout the building. • Commenced the installation of interior soffits and ceilings grid in the administration area. • Continued the installation of quarry tile in the kitchen and dishwashing area. • Continued installation of kitchen equipment. Work in Progress - Building

Work in Progress - Building (CONT.)

• Continued installation of hydronic and domestic water piping and equipment in the basement mechanical room. • Began installation of lighting in the cafeteria and kitchen areas. • Completed installation of exterior aluminum curtain wall assemblies. • Continued installation of flush wood doors in the classroom wing. • Continued installation of casework and marker boards in the classroomwing. • Completed installation of bathroom fixtures and toilet partitions in the classroomwing.

Ceiling grid and casework has commenced in the library.

December 2020

Work in Progress

• Continued installation of concrete paving. • Continued installation of stormwater conveyance and downspout tie-ins. • Completed the installation of the pre-packaged fire pump building. • Completed the installation of the propane tank farm and manifold. • Began rough grading around the loading dock area. • Maintained E&S controls. Work In Progress - Site

The propane tank farm and manifold has been installed and piping has been run to the building.

The prepackaged fire pump has been set in place.

Quarry tile in the kitchen has been installed.

Above ceiling installations are moving towards completion in the Main Office.

Finishes in the single use toilet rooms in the classroomwings are complete.

December 2020

Renderings

Building Layout First Level

Building Layout Second Level

December 2020

School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034

2019

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O

Site Milestones 1S.1 ‐ 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT ‐ 4/30 1S.3 ‐ 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 ‐ 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 ‐ 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 ‐ 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 ‐ 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 ‐ 2BS.8: Topsoil install, painting of lots and drives 3S.1 ‐ 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 ‐ 3S.7: Abatement, installation of access roads and parking lots 4S.1 ‐ 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 ‐ 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 ‐ 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1 ‐ 1B.3 ‐ Prelim prep work, excavation & site, footings & foundations

1B.4 ‐ Load bearing CMU 1B.5 ‐ Exterior wall finishes

1B.6 ‐ 1B.8 ‐ Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9 ‐ 1B.12 ‐ Construction of interior walls, MEP rough ‐ ins and equipment installation 1B.13 ‐ 1B.16 ‐ Interior & floor finishes, equipment start ‐ up & commissioning, exterior finishes.

1B.17 ‐ 1B.19 ‐ Contractor cleanup and punchlist 1B.20 ‐ 1B.21 ‐ District cleanup, setup and move in

2020

2021

D J

F M A

Current Phase and Schedule Status ‐ Site Phase 2B and Building Phase 1

1B.5 ‐ 1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 1B.10 ‐ 1B.12, 1B.15: MEP equipment piping and fixture installations 1B.13 ‐ 1B.14: Ceiling and interior paint, floor finishes, wall coverings and displays installation 2BS.3 ‐ 2BS.8: Construct fire lane, install curbing, sidewalk, new parking lot, begin landscaping 3S.6 ‐ 3S.7: Finalize installation of bus/service access road and main parking area. 1B.15, 1B.17 ‐ 1B.21: Equipment start ‐ up and commissioning,clean ‐ up and punchlist, set ‐ up/move in Issues Resolved RCN and NASD established a plan to maintain network connectivity in both buildings. PPL primary lines have been connected from the utility pole to the pad mounted transformer.

Contract Amount

Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.

$ $ $ $ $ $ $ $

5,499,330 1,157,573 29,289,026 4,080,000 1,663,000 3,341,000 118,026 20,087,000

Total Total Soft Costs: Current Remaining Project Contingency:

G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034 updated June 2020.xlsx

Report Submission Date: December 2020

Report Author: M. Evans

2020

2021

Status Comments

O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

% Complete

100% 100% 100% 95% 100% 100%

Parking lot utility work completed.

Finalized new parking and service areas. Secure site for school.

Bus driveway base paving and curbing is completed.

10% 30% 75%

Parking lot base tie ‐ in complete. Landscaping behind curbs ongoing.

Relocation/removal of contractor storage boxes.

0% 0% 0% 0% 0% 0%

Phases are scheduled for Sept. 2021 through Jan. 2022

Phase is scheduled for May 2022

Phases are scheduled for August 2022 Phases are scheduled for June ‐ July 2022

Building foundation complete. Storm Tie ‐ ins complete.

100% 100%

Load bearing CMU complete.

Brick veneer complete. Curtain walls and CMP fascia's are ongoing.

95% 98% 85% 75% 80%

Building enclosed. Roof detailing ongoing. MEP equipment installation ongoing.

Wall paint and floor finishes ongoing in Classroom wings.

Substantial Completion 5/27/21.

0%

2022

Status Comments

M J J A S O N D J

F M A M

% Complete

Install and grade subbase, install base paving where available. Ceilings, flooring and casework ongoing in the classroom wing. Exterior concrete paving and rough grading in parking area. Primary power installation by 12/11/2020. Start ‐ ups to follow. Detailing remaining on flat roof, curtain walls installed. Basement mechanical equipment piping is ongoing.

95% 85% 80% 65% 30% 10%

Issues in Progress

Paid to Date (with 10% retained)

Remaining Material Allowance

Executed Change Orders

Original Material Allowance

0 3 6 0 6 0 0 0

$ $ $ $ $ $

3,179,051 1,430,335 2,751,854 16,569,981

$ $ $ $ $ $

138,200

$ $ $ $ $ $

113,400 56,375 53,150 255,625

$ $ $ $ $ $

72,117 43,536 88,337 51,819

(148,314)

‐ ‐

9,350

9,350

23,931,221

(10,114)

487,900

265,158

Aerial Shot

December 2020

Mr. Joseph S. Kovalchik, Superintendent Mr. Matthew Sawarynski, Business Administrator Mr. Jonathan Jenny, Director of Maintenance Mrs. Cassandra Herr, Principal

School Board David Gogel, President Charles Frantz, Vice President Dr. Michael Baird

John Becker James Chuss Charles Longacre Roy Maranki Robert Mentzell Ross Makary

Construction Manager D’Huy Engineering, Inc.

Project Architect KCBA Architects

Contractors Skepton Construction, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Cyprium Solutions, Inc. Electrical Construction

Myco Mechanical, Inc. Plumbing Construction