New Lehigh Elementary School
Work in Progress - Building (CONT.)
• Continued installation of hydronic and domestic water piping and equipment in the basement mechanical room. • Began installation of lighting in the cafeteria and kitchen areas. • Completed installation of exterior aluminum curtain wall assemblies. • Continued installation of flush wood doors in the classroom wing. • Continued installation of casework and marker boards in the classroomwing. • Completed installation of bathroom fixtures and toilet partitions in the classroomwing.
Ceiling grid and casework has commenced in the library.
December 2020