New Lehigh Elementary School

Work In Progress

•Phase 2B: Interior and exterior finishes, MEP equipment installation and start-up, electrical systems and finishes. •Start: April 15, 2019 •Completion of Phase: June 15, 2021 ase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.

• Continued installation of exterior metal fascia and soffits. • Commenced the installation of aluminum gutters and downspouts. • Continued installation of lighting and electrical devices in the classroomwing. • Continued interior painting of walls and door frames throughout the building. • Commenced the installation of interior soffits and ceilings grid in the administration area. • Continued the installation of quarry tile in the kitchen and dishwashing area. • Continued installation of kitchen equipment. Work in Progress - Building