Lower Nazareth Elementary School
Report Submission Date:
11/01/20
Report Author: Lee Werkheiser
2021
2022
Status Comments
% Complete
M‐J J‐A S‐O N‐D J‐F M‐A M‐J J‐A S‐O N‐D
100% Phase 1 site work has been completed
100% Phase 1 Building addition has been completed
Under slab utilities and slab on grade complete. Load bearing CMU wall installation is ongoing
25%
0%
0%
Phase 2 aadition has begun, structural steel is placed, Demolition of existing stage has begun.
43%
0%
0%
0%
0%
g Phase 1 2020
Status Comments
M A M J J A S O N D
% Complete
TV, Data, outlet and camera location coordination with District 2 sink holes being looked into on West and North sides of Classroom addition Issues in Progress
Remaining Material Allowance
Date (with 10% etained)
2,934 $ 515,354 $ 42,270 $ 70,490 $ 43,280 $ 356,380 $ Original Material Allowance
‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ Executed Change Orders
118,302 155,192 90,364 1,175,486
356,380 $ 43,280 $ 70,490 $ 42,270 $ 2,934 $ 515,354 $
2,273
1,541,616