Construction Manager

Lower Nazareth Elementary School Nazareth Area School District

DEI Project No.017169 Monthly Progress Report No.02 November 2020

Work Completed

•Start: July 15, 2020 •Completion of Phase: April 5, 2021 Phase B1.1-B1.30: Building Phase 1

• Classroom CMU foundations and flashings completed at Classroom addition • Under slab MEP installation • EC and PC under slab inspections • Stone installation and compaction for slab in Classroom and Administration areas • Interior perimeter insulation installed • Slab prep and poured in Classroom and slab prep at Administration addition • Interior Group toilet room CMU completed • Exterior Inlet and piping placed on East side of Classroom addition • Structural steel erected at Administration addition • Demolition of existing wall for new opening for Administration area future doorway Work COmpleted

Administration Area Slab Preparation

Administration Area Steel Erection

NOvember 2020

Work Ongoing

Work Ongoing

• Submittal processing • Coordination Drawings • Installation of CMU steel bearing walls • Export of fill

• Coordination for generator relocation and conduit runs • Coordination for relocation of transformer location • Coordination of off-site inspections of steel, at fabricator shop

• Ongoing third-party inspections • Ongoing plumbing inspections • Ongoing electrical rough-in • Coordination with new electrical service • CMU interior wall layouts

• Interior door frame installations • Demo work at existing stage area

Concrete Slab Preparation

CMU Exterior Wall Placement

Concrete Slab Pour

In Wall MEP Rough-in

Interior CMUWalls

Interior Corridor CMU Placement

November 2020

Work Ongoing

New Administration Door Opening

Perimeter CMUWalls

Setting Door Frames

Stage Demolition

Steel Decking Delivery

Steel Joist Delivery

Vapor Barrier Installation

Overall Site Photo

November 2020

Building Layout

November 2020

School District:  Nazareth Area School District Project Name:  Lower Nazareth Elementary School Additions & Renovations Project Number:  017169

2020

Overall Project Schedule Status

J‐F M‐A M‐J J‐A S‐O N‐D J‐F M‐A M

Site Phase 1 S1.1 ‐ S1.12 Temp E&S, const. entr.,utility disconnect,new water line,new  ductbank,rem. grease trap,strip topsoil,inst. Basin & storm water syst.,prep building  addition pad Bldg. Phase B1.1‐B1.5 Bldg protection, disconnect bldg systems in spaces demolished,  selective demo, inst. New utilities, new conc floor, add't foundation, CMU for slab  install B1.6‐B1.14 Under slab utilities, slab‐on‐grade, load bearing CMU, roof steel, interior  CMU partitions, tie‐in roof B1.15‐1.22‐ Inst. MEP system equip & inspections, wall finishes and casework,ceiling  grid,ceiling mounted devices/fixtures,inspections,inst. flooring B1.23‐1.30 ‐ Permanent power, equip. start‐up & commissioning mech. equip., equip.  start‐up & commissioning elect., plumb, GC systems, move In B2.1‐B2.14‐Inter. Bldg. protection,select demo,inst. Add'n. Found/CMU, undersla  elect,mech,plumbing,struct steel for add'n, conc. slab on grade, fire wall,ext. shell,int.  walls,roof top equip,int. CMU walls B2.15‐B2.25 ‐ Inst. rooftop equip, roof tie‐ins, rem. temp. partitions,above ceiling  mech, elect, plumb and inspections,wall finish and casework,ceiling grid,ceiling  mounted devices/fixtures and inspections,inst.flooring B2.26‐B2.33 ‐ Rem. partition, equip. start‐up & commissioning of elect., plumb & GC  systems, sub. comp. and move‐in to admin addition B3.1‐B3.14 ‐ Abate caf and lobby,select demo, int. walls,roof top and above ceiling  mech, elect, plumb systems and inspections, int. walls finish and casework, above  ceiling mounted devices/fixtures and inspections,inst. flooring,sub. completion, final  completion Site Phase 2.1‐2.7 Inst E&S, patch conc. Sidewalks, final grade & landscaping,rem const  trailer/staging, inst. New basketball court

Building

Current Phase and Schedule Status

J A S O N D J F

B1.6‐B1.10 Install underslab electrical, mechanical & plumbing syst. CMU framing for  addition, roof steel, roof deck,concrete slab on grade B2.1‐B2.14: Installation of strutural steel, Slab on Grade and CMU walls

Issues Resolved

$               $               $               $               $               $               Paid to D re

42,082 $                      7,146,680 $                456,001 $                    1,287,597 $                939,000 $                    4,422,000 $                Contract Amount

Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: PRISM Response, LLC

Total

Report Submission Date: 

11/01/20

Report Author: Lee Werkheiser

2021

2022

Status Comments

% Complete

M‐J J‐A S‐O N‐D J‐F M‐A M‐J J‐A S‐O N‐D

100% Phase 1 site work has been completed

100% Phase 1 Building addition has been completed

Under slab utilities and slab on grade complete. Load bearing  CMU wall installation is ongoing

25%

0%

0%

Phase 2 aadition has begun, structural steel is placed,  Demolition of existing stage has begun.

43%

0%

0%

0%

0%

g Phase 1  2020

Status Comments

M A M J J A S O N D

% Complete

TV, Data, outlet and camera location coordination with District 2 sink holes being looked into on West and North sides of Classroom addition Issues in Progress

Remaining Material  Allowance

Date (with 10%  etained)

2,934 $                           515,354 $                      42,270 $                        70,490 $                        43,280 $                        356,380 $                      Original Material  Allowance

‐ $                                      ‐ $                                      ‐ $                                      ‐ $                                      ‐ $                                      ‐ $                                      Executed Change Orders

118,302 155,192 90,364 1,175,486

356,380 $                            43,280 $                              70,490 $                              42,270 $                              2,934 $                                 515,354 $                           

2,273

1,541,616

Printed 12/10/2020 1 of 2

Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr.Michael Santos, Principal

School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts

Construction Manager D’Huy Engineering, Inc.

Project Architect Alloy5 Architecture

Contractors CMG of Easton, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Wind Gap Electric, Inc. Electrical Construction

JBMMechanical, Inc. Plumbing Construction