Lower Nazareth Elementary School
School District: Nazareth Area School District Project Name: Lower Nazareth Elementary School Additions & Renovations Project Number: 017169
2020
Overall Project Schedule Status
J‐F M‐A M‐J J‐A S‐O N‐D J‐F M‐A M
Site Phase 1 S1.1 ‐ S1.12 Temp E&S, const. entr.,utility disconnect,new water line,new ductbank,rem. grease trap,strip topsoil,inst. Basin & storm water syst.,prep building addition pad Bldg. Phase B1.1‐B1.5 Bldg protection, disconnect bldg systems in spaces demolished, selective demo, inst. New utilities, new conc floor, add't foundation, CMU for slab install B1.6‐B1.14 Under slab utilities, slab‐on‐grade, load bearing CMU, roof steel, interior CMU partitions, tie‐in roof B1.15‐1.22‐ Inst. MEP system equip & inspections, wall finishes and casework,ceiling grid,ceiling mounted devices/fixtures,inspections,inst. flooring B1.23‐1.30 ‐ Permanent power, equip. start‐up & commissioning mech. equip., equip. start‐up & commissioning elect., plumb, GC systems, move In B2.1‐B2.14‐Inter. Bldg. protection,select demo,inst. Add'n. Found/CMU, undersla elect,mech,plumbing,struct steel for add'n, conc. slab on grade, fire wall,ext. shell,int. walls,roof top equip,int. CMU walls B2.15‐B2.25 ‐ Inst. rooftop equip, roof tie‐ins, rem. temp. partitions,above ceiling mech, elect, plumb and inspections,wall finish and casework,ceiling grid,ceiling mounted devices/fixtures and inspections,inst.flooring B2.26‐B2.33 ‐ Rem. partition, equip. start‐up & commissioning of elect., plumb & GC systems, sub. comp. and move‐in to admin addition B3.1‐B3.14 ‐ Abate caf and lobby,select demo, int. walls,roof top and above ceiling mech, elect, plumb systems and inspections, int. walls finish and casework, above ceiling mounted devices/fixtures and inspections,inst. flooring,sub. completion, final completion Site Phase 2.1‐2.7 Inst E&S, patch conc. Sidewalks, final grade & landscaping,rem const trailer/staging, inst. New basketball court
Building
Current Phase and Schedule Status
J A S O N D J F
B1.6‐B1.10 Install underslab electrical, mechanical & plumbing syst. CMU framing for addition, roof steel, roof deck,concrete slab on grade B2.1‐B2.14: Installation of strutural steel, Slab on Grade and CMU walls
Issues Resolved
$ $ $ $ $ $ Paid to D re
42,082 $ 7,146,680 $ 456,001 $ 1,287,597 $ 939,000 $ 4,422,000 $ Contract Amount
Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: PRISM Response, LLC
Total