Lower Nazareth Elementary School
Work Completed
•Start: July 15, 2020 •Completion of Phase: April 5, 2021 Phase B1.1-B1.30: Building Phase 1
• Classroom CMU foundations and flashings completed at Classroom addition • Under slab MEP installation • EC and PC under slab inspections • Stone installation and compaction for slab in Classroom and Administration areas • Interior perimeter insulation installed • Slab prep and poured in Classroom and slab prep at Administration addition • Interior Group toilet room CMU completed • Exterior Inlet and piping placed on East side of Classroom addition • Structural steel erected at Administration addition • Demolition of existing wall for new opening for Administration area future doorway Work COmpleted