Kenneth N. Butz, Jr. Elementary School
Report Submission Date:
December 2020
Report Author:
Lee Werkheiser
2021
2022
Status Comments
O N ‐ D J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D
% Complete
NTP issued, Shop dwgs, long lead items submitted, Temp E&S inst, Project trailers, power comp, Staging area comp, site cleared, strip topsoil comp, relocated power & water to pavilion, new fire hydrant & water line comp, Basin 002 excavated. Existing Gym Demo, MEP uitilites capped. Sanitary line inst, bldg add footings, piers & foundations inst. Underground MEP work, slab on grade comp except Gym area. Structural steel, roof deck inst above classrooms. Completed structural steel & decking. Coordination drawings completed. Roof top equipment delivered to site. Roof top curbs installed on deck of classroom addition. Coordination with slab saw cuts with Terrazzo complete. Work on Phase 2 (Nurse's Suite Addition) began early. Demo of exterior PTA room wall complete. Under slab utilities & foundations comp. Slab on grade complete. Structural steel & Roof deck comp. CMU walls completed. Fire wall completed.
90%
81%
22%
0%
85%
0%
0%
0%
E&S installed, Installed Basin 001, Poured curb and sidewalks, installed stone at new parking areas, installed berm with fill material and placed topsoil. Hydro seeded berm.
33%
Phase 1 2020
Status Comments
D J
F M A M J
J
A S O N D
% Complete
Basin 2 installation is beginning Steel is complete, CMU walls is ongoing
Started Nurse's Suite early. Steel & CMU walls complete.
Paving is wrapping up at new parking spaces
Issues in Progress
Ammended soils for basin 002 testing for percolation rates
Remaining Material Allowance
Original Material Allowance
Paid to Date (with 10% retained)
Executed Change Orders
0 0 5 0 8 3
$ $ $ $ $ $
1,640,025
$ $ $ $ $ $
‐ ‐ ‐ ‐ ‐
$ $ $ $ $ $
360,745 43,330 60,350 43,756
$ $ $ $ $ $
360,745 43,330 60,350 43,756
244,625 102,286 123,737
4,980
2,934
‐
2,115,653
‐
511,115
508,181