Construction Manager
KENNETH N. BUTZ, JR. ELEMENTARY SCHOOL Nazareth Area School District
DEI Project No.017170 Monthly Progress Report No.03 December 2020
Work Completed
•Start: August 15, 2020 •Completion of Phase: April 9, 2021 Phase 1: Classroom/Gymnasium Building Addition
Work COmpleted
• Gym perimeter columns set • Upper steel set at existing exterior classroomwalls • Basin #2 area excavated • Removal of spoils from site • Perimeter CMU of classroom areas of addition • Framing of parapet walls on Classroom addition • Nurse addition perimeter CMU
• Framing of parapet walls on Nurses addition • In wall MEP coordination in Nurses area • In wall MEP coordination of perimeter CMU Classroom addition • Coordination drawings • Coordination with District of Classroom Data and Outlets with interior elevations
• Steel decking installation at Classroom addition • Installation of Shaft wall at Nurses addition • L&I framing inspection at parapets • L&I plumbing inspection of in wall of supply and vent lines
Excavation of Basin #2
Framing Parapet Wall at Roof
December 2020
Work Ongoing
• Submittal processing • InWall Electrical Rough-in • In Stone Electrical Rough-in at Gym • Coordination of Porous Paving at new parking area • Coordination with district on construction related items that may affect traffic • Coordination of EC switchgear panel installation • Coordination and installation of MEP in-wall rough ins • Interior Classroom CMU walls • Sheathing parapet walls • Steel framing of Gym and Storage area • Basin #2 inspection of percolation of bottom of basin, prior to installing stone and piping • Placement of roof curbs for RTU units and exhaust fans • Procurement of roofing materials • Procurement of Brick Work Ongoing
Hauling Fill Off Site
Infiltration Testing at Basin #2
Mobilized Power Scaffolding
Masonry at Nurse’s Addition
Nurse’s Area Parapet Wall Framing
Nurse’s Area Shaft Wall Installation
december 2020
Work Ongoing
Perimeter North CMUWall
Placing Roof Decking on Classroom Addition
Setting Columns at Gym
Setting Upper Beam at Demising Wall
Decmeber 2020
Building Layout
Decemebr 2020
School District: Nazareth Area School District Project Name: Kenneth N. Butz, Jr. Elementary School Addition & Renovations Project Number: 017170
2020
Overall Project Schedule Status
J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O
Site Phasing Phase 1 ‐ S1.0 ‐ S1.7 ‐ Temp E&S, Staging Area, Const Entrance, Temp Power, site lighting, strip topsoil, relocate elect and water to pavilion, inst Basin 002 and storm water system
Building Phase 1 ‐ B1.0 ‐ B1.12 ‐ Existing building protective measures, Disconnect MEP for Gym Demo, Gym demo, Sanitary Demo and pour slab at Vest., Below grade foundation demo, Pad prep., Install footing and foundations, Install underslab MEP work, Erect structural steel, Install metal roof deck and roofing, Concrete slab on grade, FIre Wall Building Phase 1 ‐ B1.13 ‐ B1.19 ‐ Const ext. shell & int. CMU walls, inst rooftop equip., final roof tie ‐ ins to new & exist systems, inst mech, elect, plumbing wall mounted equip & inspections. Building Phase 1 ‐ B1.20 ‐ B1.33 ‐ Inst terrazzo flr., inst. Wall finish, casework, ceiling grid, ceiling mounted devices & fixtures, above ceiling inspections, inst. Flooring, energize perm power, equip. start ‐ up & commissioning of mech, elect, plumb & GC systems, bldg substantial completion. Building Phase 2 ‐ B2.0 ‐ 2.10 ‐ Inst int. protective measure for bldg. demo, selective demo, bldg. add'n pad & CMU for slab inst., inst. underslab elect, mech, plumb syst., erect struct. steel, metal roof deck & roofing, inst. Concrete slab on grade, const ext shell. Building Phase 2 ‐ B2.11 ‐ B2.21 ‐ Const. int. walls, inst. rooftop equip., final roof tie ‐ ins, inst. above ceiling mech, elect, plumb and wall mounted mech, elect, plumb and inspections, inst. wall finish & casework & ceiling grid, inst. ceiling mounted devices & fixtures, above ceiling inspections, inst. flooring. Building Phase 2 ‐ B2.22 ‐ B2.34 ‐ Energize perm. Power, rem int. temp partition, abatement & sel demo and in lobby and admin areas, const int. walls lobby and admin area, inst above ceiling mech, elect, plumb systems and inspections, inst. Wall mounted mech, elect, plumb equip and inspections, inst wall finish, casework, ceiling grid, inst ceiling mounted devices & fixtures and above ceiling inspections, inst flooring. Building Phase 2 ‐ B2.35 ‐ B2.37 Final Inspections, Substantial Completion & Final Completion Site Phaseing Phase 2 ‐ S2.0 ‐ S2.7 ‐ Relocate const fence, temp E&S, patch concrete sidewalks, final grading & landscaping, remove const trailers, new basketball court & repair paving S1.0 ‐ S1.7: Basin 1 finished, Basin 2 beginning, soil export continuing B1.0 ‐ B1.12: Structural Steel and Joist installation B2.0 ‐ 2.10: Strcutrual Steel placement, CMU wall construction S2.0 ‐ S2.7: Site work related to Nurse's Suite addition & additional parking has started Current Phase and Schedule Status ‐ Site Phase 1, Building Phase 1 & Building Phase 2 Issues Resolved Window in classroom 301 clash with exterior wall of classroom 503 resolved TV, Data, outlets and camera locations finalized by district and issued to contractors
J
A S O N
Contract Amount
Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: PRISM Response LLC
4,779,250
$ $ $ $ $ $
764,000
1,069,885
317,000 92,228
Total
7,022,363
Report Submission Date:
December 2020
Report Author:
Lee Werkheiser
2021
2022
Status Comments
O N ‐ D J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D
% Complete
NTP issued, Shop dwgs, long lead items submitted, Temp E&S inst, Project trailers, power comp, Staging area comp, site cleared, strip topsoil comp, relocated power & water to pavilion, new fire hydrant & water line comp, Basin 002 excavated. Existing Gym Demo, MEP uitilites capped. Sanitary line inst, bldg add footings, piers & foundations inst. Underground MEP work, slab on grade comp except Gym area. Structural steel, roof deck inst above classrooms. Completed structural steel & decking. Coordination drawings completed. Roof top equipment delivered to site. Roof top curbs installed on deck of classroom addition. Coordination with slab saw cuts with Terrazzo complete. Work on Phase 2 (Nurse's Suite Addition) began early. Demo of exterior PTA room wall complete. Under slab utilities & foundations comp. Slab on grade complete. Structural steel & Roof deck comp. CMU walls completed. Fire wall completed.
90%
81%
22%
0%
85%
0%
0%
0%
E&S installed, Installed Basin 001, Poured curb and sidewalks, installed stone at new parking areas, installed berm with fill material and placed topsoil. Hydro seeded berm.
33%
Phase 1 2020
Status Comments
D J
F M A M J
J
A S O N D
% Complete
Basin 2 installation is beginning Steel is complete, CMU walls is ongoing
Started Nurse's Suite early. Steel & CMU walls complete.
Paving is wrapping up at new parking spaces
Issues in Progress
Ammended soils for basin 002 testing for percolation rates
Remaining Material Allowance
Original Material Allowance
Paid to Date (with 10% retained)
Executed Change Orders
0 0 5 0 8 3
$ $ $ $ $ $
1,640,025
$ $ $ $ $ $
‐ ‐ ‐ ‐ ‐
$ $ $ $ $ $
360,745 43,330 60,350 43,756
$ $ $ $ $ $
360,745 43,330 60,350 43,756
244,625 102,286 123,737
4,980
2,934
‐
2,115,653
‐
511,115
508,181
Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr.Michael Santos, Principal
School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts
Construction Manager D’Huy Engineering, Inc.
Project Architect Alloy5 Architecture
Contractors CMG of Easton, Inc. General Construction
JBMMechanical, Inc. Mechanical Construction
Wind Gap Electric, Inc. Electrical Construction
JBMMechanical, Inc. Plumbing Construction