Kenneth N. Butz, Jr. Elementary School
School District: Nazareth Area School District Project Name: Kenneth N. Butz, Jr. Elementary School Addition & Renovations Project Number: 017170
2020
Overall Project Schedule Status
J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O
Site Phasing Phase 1 ‐ S1.0 ‐ S1.7 ‐ Temp E&S, Staging Area, Const Entrance, Temp Power, site lighting, strip topsoil, relocate elect and water to pavilion, inst Basin 002 and storm water system
Building Phase 1 ‐ B1.0 ‐ B1.12 ‐ Existing building protective measures, Disconnect MEP for Gym Demo, Gym demo, Sanitary Demo and pour slab at Vest., Below grade foundation demo, Pad prep., Install footing and foundations, Install underslab MEP work, Erect structural steel, Install metal roof deck and roofing, Concrete slab on grade, FIre Wall Building Phase 1 ‐ B1.13 ‐ B1.19 ‐ Const ext. shell & int. CMU walls, inst rooftop equip., final roof tie ‐ ins to new & exist systems, inst mech, elect, plumbing wall mounted equip & inspections. Building Phase 1 ‐ B1.20 ‐ B1.33 ‐ Inst terrazzo flr., inst. Wall finish, casework, ceiling grid, ceiling mounted devices & fixtures, above ceiling inspections, inst. Flooring, energize perm power, equip. start ‐ up & commissioning of mech, elect, plumb & GC systems, bldg substantial completion. Building Phase 2 ‐ B2.0 ‐ 2.10 ‐ Inst int. protective measure for bldg. demo, selective demo, bldg. add'n pad & CMU for slab inst., inst. underslab elect, mech, plumb syst., erect struct. steel, metal roof deck & roofing, inst. Concrete slab on grade, const ext shell. Building Phase 2 ‐ B2.11 ‐ B2.21 ‐ Const. int. walls, inst. rooftop equip., final roof tie ‐ ins, inst. above ceiling mech, elect, plumb and wall mounted mech, elect, plumb and inspections, inst. wall finish & casework & ceiling grid, inst. ceiling mounted devices & fixtures, above ceiling inspections, inst. flooring. Building Phase 2 ‐ B2.22 ‐ B2.34 ‐ Energize perm. Power, rem int. temp partition, abatement & sel demo and in lobby and admin areas, const int. walls lobby and admin area, inst above ceiling mech, elect, plumb systems and inspections, inst. Wall mounted mech, elect, plumb equip and inspections, inst wall finish, casework, ceiling grid, inst ceiling mounted devices & fixtures and above ceiling inspections, inst flooring. Building Phase 2 ‐ B2.35 ‐ B2.37 Final Inspections, Substantial Completion & Final Completion Site Phaseing Phase 2 ‐ S2.0 ‐ S2.7 ‐ Relocate const fence, temp E&S, patch concrete sidewalks, final grading & landscaping, remove const trailers, new basketball court & repair paving S1.0 ‐ S1.7: Basin 1 finished, Basin 2 beginning, soil export continuing B1.0 ‐ B1.12: Structural Steel and Joist installation B2.0 ‐ 2.10: Strcutrual Steel placement, CMU wall construction S2.0 ‐ S2.7: Site work related to Nurse's Suite addition & additional parking has started Current Phase and Schedule Status ‐ Site Phase 1, Building Phase 1 & Building Phase 2 Issues Resolved Window in classroom 301 clash with exterior wall of classroom 503 resolved TV, Data, outlets and camera locations finalized by district and issued to contractors
J
A S O N
Contract Amount
Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: PRISM Response LLC
4,779,250
$ $ $ $ $ $
764,000
1,069,885
317,000 92,228
Total
7,022,363
Made with FlippingBook - Online Brochure Maker