Kenneth N. Butz, Jr. Elementary School
Work Completed
•Start: August 15, 2020 •Completion of Phase: April 9, 2021 Phase 1: Classroom/Gymnasium Building Addition
Work COmpleted
• Gym perimeter columns set • Upper steel set at existing exterior classroomwalls • Basin #2 area excavated • Removal of spoils from site • Perimeter CMU of classroom areas of addition • Framing of parapet walls on Classroom addition • Nurse addition perimeter CMU
• Framing of parapet walls on Nurses addition • In wall MEP coordination in Nurses area • In wall MEP coordination of perimeter CMU Classroom addition • Coordination drawings • Coordination with District of Classroom Data and Outlets with interior elevations
• Steel decking installation at Classroom addition • Installation of Shaft wall at Nurses addition • L&I framing inspection at parapets • L&I plumbing inspection of in wall of supply and vent lines