KENNETH N. BUTZ, JR. ELEMENTARY SCHOOL Nazareth Area School District

DEI Project No.017170 Monthly Progress Report No.03 December 2020

Work Completed

•Start: August 15, 2020 •Completion of Phase: April 9, 2021 Phase 1: Classroom/Gymnasium Building Addition

Work COmpleted

• Gym perimeter columns set • Upper steel set at existing exterior classroomwalls • Basin #2 area excavated • Removal of spoils from site • Perimeter CMU of classroom areas of addition • Framing of parapet walls on Classroom addition • Nurse addition perimeter CMU

• Framing of parapet walls on Nurses addition • In wall MEP coordination in Nurses area • In wall MEP coordination of perimeter CMU Classroom addition • Coordination drawings • Coordination with District of Classroom Data and Outlets with interior elevations

• Steel decking installation at Classroom addition • Installation of Shaft wall at Nurses addition • L&I framing inspection at parapets • L&I plumbing inspection of in wall of supply and vent lines

Excavation of Basin #2

Framing Parapet Wall at Roof

December 2020

Work Ongoing

• Submittal processing • InWall Electrical Rough-in • In Stone Electrical Rough-in at Gym • Coordination of Porous Paving at new parking area • Coordination with district on construction related items that may affect traffic • Coordination of EC switchgear panel installation • Coordination and installation of MEP in-wall rough ins • Interior Classroom CMU walls • Sheathing parapet walls • Steel framing of Gym and Storage area • Basin #2 inspection of percolation of bottom of basin, prior to installing stone and piping • Placement of roof curbs for RTU units and exhaust fans • Procurement of roofing materials • Procurement of Brick Work Ongoing

Hauling Fill Off Site

Infiltration Testing at Basin #2

Mobilized Power Scaffolding

Masonry at Nurse’s Addition

Nurse’s Area Parapet Wall Framing

Nurse’s Area Shaft Wall Installation

december 2020

Work Ongoing

Perimeter North CMUWall

Placing Roof Decking on Classroom Addition

Setting Columns at Gym

Setting Upper Beam at Demising Wall

Decmeber 2020

Building Layout

Decemebr 2020

School District: Nazareth Area School District Project Name: Kenneth N. Butz, Jr. Elementary School Addition & Renovations Project Number: 017170

2020

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J

J ‐ A S ‐ O

Site Phasing Phase 1 ‐ S1.0 ‐ S1.7 ‐ Temp E&S, Staging Area, Const Entrance, Temp Power, site lighting, strip topsoil, relocate elect and water to pavilion, inst Basin 002 and storm water system

Building Phase 1 ‐ B1.0 ‐ B1.12 ‐ Existing building protective measures, Disconnect MEP for Gym Demo, Gym demo, Sanitary Demo and pour slab at Vest., Below grade foundation demo, Pad prep., Install footing and foundations, Install underslab MEP work, Erect structural steel, Install metal roof deck and roofing, Concrete slab on grade, FIre Wall Building Phase 1 ‐ B1.13 ‐ B1.19 ‐ Const ext. shell & int. CMU walls, inst rooftop equip., final roof tie ‐ ins to new & exist systems, inst mech, elect, plumbing wall mounted equip & inspections. Building Phase 1 ‐ B1.20 ‐ B1.33 ‐ Inst terrazzo flr., inst. Wall finish, casework, ceiling grid, ceiling mounted devices & fixtures, above ceiling inspections, inst. Flooring, energize perm power, equip. start ‐ up & commissioning of mech, elect, plumb & GC systems, bldg substantial completion. Building Phase 2 ‐ B2.0 ‐ 2.10 ‐ Inst int. protective measure for bldg. demo, selective demo, bldg. add'n pad & CMU for slab inst., inst. underslab elect, mech, plumb syst., erect struct. steel, metal roof deck & roofing, inst. Concrete slab on grade, const ext shell. Building Phase 2 ‐ B2.11 ‐ B2.21 ‐ Const. int. walls, inst. rooftop equip., final roof tie ‐ ins, inst. above ceiling mech, elect, plumb and wall mounted mech, elect, plumb and inspections, inst. wall finish & casework & ceiling grid, inst. ceiling mounted devices & fixtures, above ceiling inspections, inst. flooring. Building Phase 2 ‐ B2.22 ‐ B2.34 ‐ Energize perm. Power, rem int. temp partition, abatement & sel demo and in lobby and admin areas, const int. walls lobby and admin area, inst above ceiling mech, elect, plumb systems and inspections, inst. Wall mounted mech, elect, plumb equip and inspections, inst wall finish, casework, ceiling grid, inst ceiling mounted devices & fixtures and above ceiling inspections, inst flooring. Building Phase 2 ‐ B2.35 ‐ B2.37 Final Inspections, Substantial Completion & Final Completion Site Phaseing Phase 2 ‐ S2.0 ‐ S2.7 ‐ Relocate const fence, temp E&S, patch concrete sidewalks, final grading & landscaping, remove const trailers, new basketball court & repair paving S1.0 ‐ S1.7: Basin 1 finished, Basin 2 beginning, soil export continuing B1.0 ‐ B1.12: Structural Steel and Joist installation B2.0 ‐ 2.10: Strcutrual Steel placement, CMU wall construction S2.0 ‐ S2.7: Site work related to Nurse's Suite addition & additional parking has started Current Phase and Schedule Status ‐ Site Phase 1, Building Phase 1 & Building Phase 2 Issues Resolved Window in classroom 301 clash with exterior wall of classroom 503 resolved TV, Data, outlets and camera locations finalized by district and issued to contractors

J

A S O N

Contract Amount

Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: PRISM Response LLC

4,779,250

$ $ $ $ $ $

764,000

1,069,885

317,000 92,228

Total

7,022,363

Report Submission Date:

December 2020

Report Author:

Lee Werkheiser

2021

2022

Status Comments

O N ‐ D J ‐ F M ‐ A M ‐ J

J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J

J ‐ A S ‐ O N ‐ D

% Complete

NTP issued, Shop dwgs, long lead items submitted, Temp E&S inst, Project trailers, power comp, Staging area comp, site cleared, strip topsoil comp, relocated power & water to pavilion, new fire hydrant & water line comp, Basin 002 excavated. Existing Gym Demo, MEP uitilites capped. Sanitary line inst, bldg add footings, piers & foundations inst. Underground MEP work, slab on grade comp except Gym area. Structural steel, roof deck inst above classrooms. Completed structural steel & decking. Coordination drawings completed. Roof top equipment delivered to site. Roof top curbs installed on deck of classroom addition. Coordination with slab saw cuts with Terrazzo complete. Work on Phase 2 (Nurse's Suite Addition) began early. Demo of exterior PTA room wall complete. Under slab utilities & foundations comp. Slab on grade complete. Structural steel & Roof deck comp. CMU walls completed. Fire wall completed.

90%

81%

22%

0%

85%

0%

0%

0%

E&S installed, Installed Basin 001, Poured curb and sidewalks, installed stone at new parking areas, installed berm with fill material and placed topsoil. Hydro seeded berm.

33%

Phase 1 2020

Status Comments

D J

F M A M J

J

A S O N D

% Complete

Basin 2 installation is beginning Steel is complete, CMU walls is ongoing

Started Nurse's Suite early. Steel & CMU walls complete.

Paving is wrapping up at new parking spaces

Issues in Progress

Ammended soils for basin 002 testing for percolation rates

Remaining Material Allowance

Original Material Allowance

Paid to Date (with 10% retained)

Executed Change Orders

0 0 5 0 8 3

$ $ $ $ $ $

1,640,025

$ $ $ $ $ $

‐ ‐ ‐ ‐ ‐

$ $ $ $ $ $

360,745 43,330 60,350 43,756

$ $ $ $ $ $

360,745 43,330 60,350 43,756

244,625 102,286 123,737

4,980

2,934

2,115,653

511,115

508,181

Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr.Michael Santos, Principal

School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts

Construction Manager D’Huy Engineering, Inc.

Project Architect Alloy5 Architecture

Contractors CMG of Easton, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Wind Gap Electric, Inc. Electrical Construction

JBMMechanical, Inc. Plumbing Construction