Whitehall Coplay School District New K-1 Elementary School

Animated publication

New K-1 Elementary School Whitehall Coplay School District DEI Project No. 281003 Monthly Progress Report No. 2 May 2022

New K-1 Elementary School Whitehall Coplay S

SITE PHASING PLAN S1: Site Preparation, Complete Structure Demolition, Utility Capping and Relocations

Start: April 2022 Completion: June 2022

WORK COMPLETED AND COMMENCING

• Completion of all utility terminations serving existing administrative building and barn structures in preparation for structure demolition. • Coordination and scheduling the relocating of PPL’s main underground electrical transmission line and underground communications lines to allow for the construction of a new stormwater subsurface detention system. • Installation of the site staging area and temporary electrical service. • Installation of new sanitary storm sewer main from the public library parking lot to future tie-in location of high school and new building system. • Stripping of topsoil around existing buildings in preparation for structure demolition. • Complete structure demolition has begun on the former administration building. • Crushing of the demolished masonry and concrete will begin on-site. This material will be used as structural fill in the construction of the new building. • Site Phasing Plan S2 is scheduled to begin at the end of June. This will include the excavation of the building pad, rough grading of the entire site, and installation of 2 temporary stormwater sediment traps. • Building Phasing Plan B1 is scheduled to begin with foundation excavation the week of July 18th.

School District

New sanitary sewer main installation MH1-MH2.

New sanitary sewer main installation MH-MH1.

Demolition of Administration Building.

May 2022

New K-1 Elementary School Whitehall Coplay S

Completed installation of temporary construction staging area.

School District

May 2022

New K-1 Elementary School Whitehall Coplay S

School District: Whitehall-Coplay School District Project Name: New K-1 Elementary School Project Number: 281003

2022

Overall Project Schedule Status

A M J J A S O N D J-

Site Work Phase 1 Site Work Phase 2 Phase 1 - Building Construction Phase 2 - Core Space Building construction Owner Occupancy / Closeout

2022

Current Phase and Schedule Status

J

A M J J A S O N D

Site Work Phase 1

Install staging and storm water basins Relocate existing underground communications, electric and water lines Demolish and remove existing Admin bldg., barn and other storage bldgs. Site Work Phase 2 Excavate for Building Pad, Import structural fill, rough grade site Install utilities Construct parking areas, driveways, sidewalks and playground Phase 1 - Building Construction Foundations, Slab on grade construction Exterior walls, Roof (Watertight) Interior Partitions, MEP Fixtures and Equipment Phase 2 - Core Space Building Construction Core Space Construction and Finishes Final termination of utility companies lines to allow for structure demolition to begin. Stormwater HDPE pipe substitution approved to improve lead times. Issues Resolved

Executed change orders for building permits.

Contract Amount 22,265,000 $

Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric Plumbing Contractor: Vision Mechanical ATC Contractor: Johnson Controls

$ $ $ $ $ $

$ $ $ $ $ $ $

3,551,000 3,758,000 1,722,000 687,500 31,983,500 7,959,650 2,000,000

Total Total Soft Costs: Current Remaining Project Contingency

School District

Report Submission Date:

May 2022

Report Author:

Chris Haller

2023

2024

Status Comments

-F M-A M-J J-A S-O N-D J F M A M J

J

% Complete

35%

2023

2024

Status Comments

J F M A M J

J A S O N D J

% Complete

35% 25% 25% 15%

Installed staging area and new sanitary main line

PP&L and Communication relocation scheduled for end of June

Structure demolition began week of 5/30/2022

Ductile iron pipe lead times for installation of relocated water main. Issues in Progress

Paid to Date (with 10% retained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $ $

67,500 939,524

$ $ $ $ $ $

27,730

$ $ $ $ $ $

104,350 396,050 86,135 66,290 687,500

$ $ $ $ $ $

396,050 104,350 86,135 66,290 687,500

7,815

-

- - -

23,675

-

1,030,699

35,544

1,340,325

1,340,325

May 2022

Dr. Robert Steckel, Jr. – Superintendent Christopher Schiffert – Assistant to the Superintendent J. Michael Malay, Jr. – Business Manager Stephen Seier – Director of Educational Operations Phil Bankos – Supervisor of Buildings and Grounds

WCSD Board of Directors William Fonzone, Sr. President George Makhoul, Vice President Patty Gaugler, Member Nichole Hartman, Member Keri Kromer, Member Fady Salloum, Member Allison Schultz, Member Joseph Shields, Member George Williams, Treasurer

Construction Manager – D’Huy Engineering Project Architect – Breslin Architects

Contractors Skepton Construction Inc. General Contractor

JBMMechanical Mechanical Contractor

Wind Gap Electric Inc. Electric Contractor

Vision Mechanical Inc. Plumbing Contractor