WCSD New K-1 Elementary School
New K-1 Elementary School Whitehall Coplay S
School District: Whitehall-Coplay School District Project Name: New K-1 Elementary School Project Number: 281003
2022
Overall Project Schedule Status
A M J J A S O N D J-
Site Work Phase 1 Site Work Phase 2 Phase 1 - Building Construction Phase 2 - Core Space Building construction Owner Occupancy / Closeout
2022
Current Phase and Schedule Status
J
A M J J A S O N D
Site Work Phase 1
Install staging and storm water basins Relocate existing underground communications, electric and water lines Demolish and remove existing Admin bldg., barn and other storage bldgs. Site Work Phase 2 Excavate for Building Pad, Import structural fill, rough grade site Install utilities Construct parking areas, driveways, sidewalks and playground Phase 1 - Building Construction Foundations, Slab on grade construction Exterior walls, Roof (Watertight) Interior Partitions, MEP Fixtures and Equipment Phase 2 - Core Space Building Construction Core Space Construction and Finishes
Repairs of sinkholes discovered during building demolition. Stormwater HDPE pipe substitution approved to improve lead times. Pipe was delivered and installation has begun. Issues Resolved
Contract Amount 22,265,000 $
Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric Plumbing Contractor: Vision Mechanical ATC Contractor: Johnson Controls
$ $ $ $ $ $
$ $ $ $ $ $ $
3,551,000 3,758,000 1,722,000 687,500 31,983,500 7,959,650 2,000,000
Total Total Soft Costs: Current Remaining Project Contingency