Projected Progress for April 2022
• Complete edge metal, fascia, gutters, downspouts and soffits. • Complete any repairs for urethane cement floor installation in apparatus bay. • Test and inspect fire pump for sprinkler start up. • Complete plumbing fixture installation. • Complete remaining device install for fire alarm and fire alerting systems. • Complete above ceiling inspections and drop all remaining ceiling tile. • Complete touch up paint. • Complete furniture installation. • Complete roof top sheet and gravel.
• Continue final architectural punch lists. • Begin MEP system start up where possible. • Spread topsoil and begin landscaping. • Place wearing course of pavement. • Site cleanup.
Metal roof complete. Exterior metal panels nearing completion.
Generator set.