Upper Providence Township, New Central Station Emergency Services Township

Report Submission Date: August 2021

Report Author: Michael DePodwin

021

2022

J

A S O N

D J

F M A M J

% Complete

Status Comments

Slab on Grade and Structural Steel detailing ongoing Exterior block wall isntallation ongoing Interior block wall and MEP rough‐in ongoing Resubmittals nearing completion

90% 40% 75% 95%

0% 0% 0%

Fence to be completed

50% 90% 99%

Underground rough‐in nearing completion Curbs complete, stone base nearing completion Stabilization of site complete

0% 0% 0% 5%

Phase 1 2021

Status Comments

J A S O N D J F M A M J

% Complete

50% 50% 95% 90%

All utilities have been terminated building side save for gas. Rough‐ins nearing completion Area B slab on grade complete Area A slab on grade ongoing. Erection and detailing nearing completion.

90% Exterior walls nearing completion 90% 5% Roof blocking underway

80% Interior walls ongoing

Issues in Progress

Complete a building low voltage, security, and access control design with GKO and CEI. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Work with Vision Mechanical on resolving sprinkler shops drawings and calculations.

Work with Lobar on roof nailboard and stone veneer procurement.

Paid to Date (with 10% retained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $

3,560,815

$ $ $ $ $

‐ ‐ ‐ ‐

$ $ $ $ $

209,365 47,807 94,098 37,920 389,190

$ $ $ $ $

189,198 47,807 92,910 64,622 394,537

129,598 360,850 360,188

4,411,451

1% Submittals

Requests for Information

0%

Approved Rejected Voided Overdue

2% 0%

12%

0%

Complete Outstanding Voided

87%

98%