Upper Providence Township, New Central Station Emergency Services Township
New Central Emergency Services Facility
Projected Progress for Sept. 2021
• Complete interior masonry wall installation and in-wall electrical rough-ins. • Complete exterior masonry wall installation. • Complete under slab MEP installation including the interior section of the apron
heating system and apparatus bay trench drains. • Complete erection and detailing of structural steel. • Complete all concrete slab pours. • Complete concrete curb installation and road subgrade. • Begin installation of 2-ply membrane roof. • Complete mechanical duct and pipe hanger installation. • Begin overhead MEP rough-in in apparatus bay.
Trench Drain Installation Nearing Completion
Roadway Sub-base ongoing.