Construction Manager
New Central Emergency Services Facility Upper Providence Township
DEI Project No.720001 Monthly Progress Report No.08 December 2021
New Central Emergency Services Facility
CURRENT MILESTONES DATES: Complete: P1.1 – P1.23 Complete MEP System Placement (12/23/21) Ongoing: P1.24 – P1.32 Energize Permanent Power (02/07/22) Complete Fire Alarm, Security System (02/04/22) Install Ceiling Grid & Hard Ceilings (01/25/22) Install Ceiling Mounted Devices (01/31/22) Install Floor Finishes (02/18/22)
Site Construction Progress
• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Place asphalt at inner loop road. • Complete light pole base installation. • Rebar and radiant heat installation complete at front and rear concrete aprons. • Complete sidewalk stone preparation. Site Construction Progress
Building Construction Progress
• Begin exterior stone and brick veneer. • Overhead rough-ins of mechanical, plumbing, gas pipe, electrical nearing completion. • Continue sprinkler rough-ins. • Complete electrical branch wiring.
• Continue installation of window frames and glazing. • Continue ceiling grid perimeters and bulkhead layouts. • Complete mechanical and plumbing insulation. • Complete raised access flooring in Training, E.O.C. Room • Place concrete at generator corral and patio.
y
Patio concrete placed.
Mezzanine MEP Placement Complete.
December 2021
New Central Emergency Services Facility
Projected Progress for Jan. 2022
• Complete installation of exterior brick veneer and stone. • Complete interior stone veneer. • Complete installation of storefront system. • Complete concrete front and rear apparatus bay aprons and sidewalks. • Complete installation of roof and exterior wall metal panels. • Install rear apparatus bay doors. • Begin edge metal, fascia, gutters, and soffits. • Begin casework installation. • Begin resinous floor and ceramic tile installation in living quarters.
• Complete hard ceilings and ceiling grid. • Complete plumbing fixture installation. • Place all grilles, registers, and diffusers. • Place all interior light fixtures.
Resinous flooring installation ongoing.
Exterior brick veneer installation ongoing.
y
Rebar installation complete for exterior concrete aprons.
Day room above ceiling work nearing completion.
December 2021
Building Layout
Aerial view of building and material laydown area (December 2021).
Site Overview (December 2021).
Building Floor Plan
Building Site Plan
December 2021
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001 Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001 Building Milestones P1.1-P1.2 - Notice to Proceed, Shop Drawings, Submittals Overall Project Schedule Status Overall Project Schedule Status
202
J
F M A M J
2021
P1.12-P1.17 - Building Pad, Foundations, Structural Steel, Slab on Grade P1.18-P1.19 - Exterior Masonry walls, Waterproofing, Roof structure P1.20-P1.24 - Interior Partitions, MEP system placement P1.25-P1.33 - Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP Commissioning P1.34-P1.36 - Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 - P1.40 - Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move-in Site Milestones P1.3-P1.11 - Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 - Installation of Site Lighting Bases and Lights P1.42 - Curbing and Stone base for Parking Lots and Sidewalk installation P1.43-P1.44 - Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, EP C mmissioning 34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Own r Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milesto es P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping P1.45-P1.46 - Final Grading and Site Signage, Paving P1.47-P1.48 - Demolish existing structure, Paving P1.54-P1.55 - Project Substantial and Final Completion P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion Current Phase and Schedule Status
J
F M A M J
J
J F M A M J
P1.21-23 - Complete Placement of MEP Systems P1.24 - Energize Permanent Power P1.25 - Complete Painting of Walls P1.26 - Install Ceiling Grid and Complete Hard Ceilings P1.27 - Ceiling Mounted Devices and Lighting P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems Current Phase and Schedule Status P1.28 - Plymavent System P1.29 - Complete Casework P1.30 - Install Ceiling Tile
J F M A M J J
Issues Resolved Coordinate the radiant heat piping and rebar placement at the concrete aprons. P1.24 ‐ Energize Permanent Power P1.25 ‐ Complete Painting of Walls P1.26 ‐ Install Ceiling Grid and Complete Hard Ceilings Issues Resolved Work with Vision Mechanical on resolving sprinkler shop darwings and calculations. Coordinate with Lobar on roof nail board and stone veneer procurement. Coordinate the FF&E process with GKO and the Township. Complete building low voltage, security, and access control design with GKO and CEI. Complete the FF&E process with GKO and the Township. Schedule and coordination of the Plymovent exhaust system
Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri-County Mechanical, Inc. Electrical Contractor: Electri-Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc. Co tr ct General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.
Contract Amount
$ $ $ $ $
10,719,597 1,123,000 1,2 2,400 1,212,400 922,197 1,123,000 7,462,000 7,462,000
$ $ $ $ $
Contract Amount
$ $ $ $ $
Total Total Soft Costs: Current Remaining Project Contingency Total Total Soft Costs: Current Remaining Project Contingency
$ $
922,197
10,719,597
Other Discussion
Other Discussion
Report Submission Date: December 2021
Report Author: Michael DePodwin Report Submission Date: November 2021
21
2022
J
A S O N
D J
F M A M J
% Complete
Status Comments
Report Author: Michael DePodwin
Resubmittals nearing completion
1
2022
99%
Complete Complete Complete Stabilization of site complete Base and binder paving courses complete. Slab on Grade and Structural Steel complete. Exterior walls complete. Roof weathertight. Interior block wall complete. MEP rough‐in ongoing Interior block filler ongoing. Fence to be completed All light pole bases installed. Light pole installation ongoing Complete Stabilization of site complete Base and binder paving courses complete. Slab on Grade and Structural Steel complete. Final roof metal outstanding Interior block wall complete. MEP rough-in nearing completion First paint coat complete. Grid installation ongoing. MEP fit-out begun. Status Comments Resubmittals nearing completion
100% 95% 99%
A S O N
D J
F M A M J
% Complete
99%
100% 90% 90%
75% 0% 0%
10% 0% 0%
100% 100% 100%
99%
25% 65%
90% 100%
0% 0%
25% 60%
Phase 1 2021
Status Comments
0% 0%
J A S O N D J F M A M J
% Complete
99% 95% 75%
Nearing Completion Waiting on MDP delivery.
Phase 1 2021
Status Comments
A S O N D J F M A M J
% Complete
Block filler and first coat complete.
100% 100%
Complete Complete
90% Nearing Completion
15% To be completed after apparatus bay flooirng 10% 0% To be completed in January 2022 Device installation underway. Roof weathertight. Metal roof and cap sheet outstanding. Complete All system installation ongoing. 5% Ceiling tile edge installation begun.
80%
100%
95% Nearing completion 80% 10% Block filler underway
Issues in Progress
Continue Coordinate ASI 11 work with ETI, ETI's controls subcontractor, and UPT's security vendor. Expedite the installation of PECO gas line and delivery of MDP to have permanent power on site. Continue to monitor Erosion & Sedimentation Controls. Ensure site hours, noise, and lighting are compliant with Township ordinances. 0% Issues in Progress Review cost proposal from ETI regarding low voltage, security, and access control changes. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Ensure site hours, noise, and lighting are compliant with Township ordinances. Continue to track equipment and material procurement to ensure critical path remain on schedule. Executed Change Orders Original Material Allowance
Paid to Date (with 10% retained) Paid to Date (with 10% retained)
Remaining Material Allowance
$ $ $ $ $
184,489 47,807 98,883 64,622 395,800
$ $ $ $ $
8,032,228 482,268 53 ,674 957,604 676,009 734,478 5,664,136
$ $ $ $ $
- - - - -
$ $ $ $ $
389,190 37,920 94,098 47,807 209,365
Original Material Allowance
Remaining Material Allowance
Executed Change Orders
4,818,025
$ $ $ $ $
‐ ‐ ‐ ‐
$ $ $ $ $
209,365
$ $ $ $ $
184,489 47,807
47,80
389,190 37,920 94,098
98,88
476,034
64,622 395,800
6,310,001
‐
0% Submittals
Requests for Information
0%
12% 0% Submittals
0% Requests for Information
Approved Rejected Voided Overdue
0%
Complete Outstanding Voided Overdue
0%
Approved Rejected Voided Overdue
5% 0
13%
Complete Outstanding Voided Overdue
88%
0%
95%
2%
87%
98%
Tim Tieperman – Township Manager Bryan Bortnichak – Assistant Township Manager Dan Kerrigan – Chief of Fire And Emergency Services
Board of Supervisors Bill Starling – Chair Helene Calci – Vice Chair
Laurie Higgins John Pearson Tom Yeager
Construction Manager D’huy Engineering, Inc.
Project Architect Gko Architects, Llc
Civil Engineer Gilmore & Associates, Inc.
Contractors Lobar, Inc. General Construction
Tri-County Mechanical, Inc. Mechanical Construction
Electri-Tech, Inc. Electrical Construction
Vision Mechanical, Inc. Plumbing Construction