Upper Providence Township
New Central Emergency Services Facility
CURRENT MILESTONES DATES: Complete: P1.1 – P1.23 Complete MEP System Placement (12/23/21) Ongoing: P1.24 – P1.32 Energize Permanent Power (02/07/22) Complete Fire Alarm, Security System (02/04/22) Install Ceiling Grid & Hard Ceilings (01/25/22) Install Ceiling Mounted Devices (01/31/22) Install Floor Finishes (02/18/22)
Site Construction Progress
• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Place asphalt at inner loop road. • Complete light pole base installation. • Rebar and radiant heat installation complete at front and rear concrete aprons. • Complete sidewalk stone preparation. Site Construction Progress
Building Construction Progress
• Begin exterior stone and brick veneer. • Overhead rough-ins of mechanical, plumbing, gas pipe, electrical nearing completion. • Continue sprinkler rough-ins. • Complete electrical branch wiring.
• Continue installation of window frames and glazing. • Continue ceiling grid perimeters and bulkhead layouts. • Complete mechanical and plumbing insulation. • Complete raised access flooring in Training, E.O.C. Room • Place concrete at generator corral and patio.