Northampton Township

Report Submission Date:

10/24/22

Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001

Report Author:

Colin Case

2023

Status Comments

J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

% Complete

Overall Project Schedule Status

30% Building Pad Completed

July 2022 thru July 2023

Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roo P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Ca MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Pun P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Co Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidew P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Co P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems P1.24 ‐ Energize Permanent Power P1.25 ‐ Complete Painting of Walls P1.26 ‐ Install Ceiling Grid and Complete Hard Ceilings Issues Resolved Work with Vision Mechanical on resolving sprinkler Coordinate with Lobar on roof nail board and stone Coordinate the FF&E process with GKO and the Tow Complete building low voltage, security, and access Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc. Current Phase and Schedule Status

Foundations and underground M.E.P. complete. Slab on grade to be poured after structural steel completes.

90%

25% Steel erection is in progress.

November 2022 thru January 2023

January 2023 thru March 2023

February 2023 thru April 2023

March 2023 thru May 2023

April 2023 thru July 2023

July 2023

veout extension and adjusted milestones per the GC's CPM schedule.

2022 ‐ 2023

Status Comments

A S O N D J F M A

% Complete

100% Completed

Basin B1 completed. New utilities to be installed during the month of November.

75%

20% Building Pad Completed

60%

Foundations and underground M.E.P. complete. Slab on grade to be poured after structural steel completes.

90%

25% Steel erection is in progress.

Issues in Progress

Other Discussion

Cell Service providers have not provided a relocation schedule for their utilities serving the cell tower building PECO has not provided a installation scheudule for the electric or gas services

Printed 10/25/2022 1 of 1