Northampton Township Fire Station #3 Project Number: 721001

2022

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B3.1 to B3.4 ‐ Place foundations. Complete under slab MEP rough ‐ in. Complete slab on grade and cure time. B3.5 to B3.7 ‐ Erect structural steel. Complete masonry walls. Complete roof (building to be watertight).

B3.8 to B3.12 ‐ Complete interior CMU walls, metal studs. Complete in ‐ wall MEP rough ‐ ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough ‐ ins.

B3.13 to B3.16 ‐ Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B3.17 to B3.20 ‐ Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B3.21 to B3.23 ‐ Complete fire alarm and security system. MEP start ‐ up.. Complete elevator inspection. B3.24 to B3.27 ‐ Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B3.28 to B3.30 ‐ Substantial completion, Final completion. Owner furniture, fixtures and equipment move ‐ in and occupy. S3.1 to S3.6 ‐ NTP,process shop dwgs/submittal/begin procurement Disconnect exist utilities to exist Fire Station. Install temp E&S/construction fence,protect communication tower, install staging area,construction entrance,construction trailers,temp. S3.7 to S3.11 ‐ Demo existing fire station incl footings, foundations. Provide protection for cell town bldg. Fill void from basement. Route new utilities for tower. Inst. Stormwater basin and storm sewer piping. S3.12 to S3.15 ‐ Prepare bldg pad, inst. Undergrnd electric, gas to bldg. pad. Inst. San. Sewer/water piping and connect to street S3.16 to S3.18 ‐ Complete rough grading, inst. ret. walls, ext. light bases, post, lights. Inst. concrete curbs/sidewalks incl. work along Township Road. B3.1 to B3.4 ‐ Place foundations. Complete under slab MEP rough ‐ in. Complete slab on grade and cure time. B3.5 to B3.7 ‐ Erect structural steel. Complete masonry walls. Complete roof (building to be watertight). Current Building Phase: Current Site Phase: Current Phase and Schedule Status

Milestones have been adjusted to account for the 30 ‐ day Owner mov

F M A M J

J

Issues Resolved

Underpinning of existing cell tower was completed on 9/1 New electrical service will be run under the road rather than overhead to the site.