Northampton Township New Firestation #3 and New Firestation #73

WORK COMPLETED STATION #73

• Processed shop drawings and submittals. • Began procurement of items with long lead times. • Established weekly superintendent construction meetings. • Installed construction entrances and fencing. • Installed Phase 1 Erosion & Sediment Controls. • Installed construction staging area. • Established construction trailers and temporary power. • Installed Protections for VerizonWireless Building.

• Completed Demolition of existing building structure and foundations. • Separated and processed materials from the building demolition. • Began site clearing. • Removed unsuitable soils and completed construction of the building pad. • Began placement of foundations.

Station #73 Building Foundations

Station #73 Structure Demolition

Station #73 Demo and Building Pad Preparation

Station #73 Existing Fuel Tank Removal

May 2022