Northampton Township New Firestation #3 and New Firestation #73

Animated publication

NEW FIRE STATION #3 AND NEW FIRE STATION #73 Northampton Township DEI Project No. 721001 Monthly Progress Report No. 1 May, 2022

NEW FIRE STATION #3 AND NEW FIRE STATION #73

FIRE STATION #3 Current Site Milestones: S3.1-S3.15: (3/22 – 9/22) Current Building Milestones: B3.1-B3.4: (7/22-9/22)

Station #3 Aerial

FIRE STATION #73 Current Site Milestones: S73.1-S73.15: (3/22 – 9/22) Current Building Milestones: B73.1-B73.4: (7/22-9/22)

Station #73 Aerial

May 2022

NEW FIRE STATION #3 AND NEW FIRE STATION #73

WORK COMPLETED STATION #3

• Conducted construction kick-off meetings with the construction team and Bucks County Conservation District. • Began submission and review of shop drawings and submittals.

• Began procurement of items with long lead times. • Began 3D modeling and coordination drawings. • Established weekly superintendent construction meetings. • Completed Owner move out.

• Completed construction entrances and fencing. • Installed Phase 1 Erosion & Sediment Controls. • Scanned and located all existing underground utilities to the existing building and cell site. • Installed construction staging area. • Established construction trailers and temporary power. • Installed Protections for the communications tower and associated facilities. • Completed Demolition of existing building structure and foundations. • Separated and processed materials from the building demolition. • Began site clearing. • Began coordinating the relocation of cell site existing underground utilities. • Began Construction of the building pad

Station #3 Structural Demolition

Station #3 Cell Tower Temporary Protections

Station #3 Demolition

WORK COMPLETED STATION #73

• Processed shop drawings and submittals. • Began procurement of items with long lead times. • Established weekly superintendent construction meetings. • Installed construction entrances and fencing. • Installed Phase 1 Erosion & Sediment Controls. • Installed construction staging area. • Established construction trailers and temporary power. • Installed Protections for VerizonWireless Building.

• Completed Demolition of existing building structure and foundations. • Separated and processed materials from the building demolition. • Began site clearing. • Removed unsuitable soils and completed construction of the building pad. • Began placement of foundations.

Station #73 Building Foundations

Station #73 Structure Demolition

Station #73 Demo and Building Pad Preparation

Station #73 Existing Fuel Tank Removal

May 2022

Building Layout: Station #3

May 2022

Building Layout: Station #73

May 2022

Station #3

P a g e | 5 Northampton Township Fire Station #3 Project Number: 721001

2022

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J ‐ J A

‐ S O

‐ N D ‐ J F

Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B3.1 to B3.4 ‐ Place foundations. Complete under slab MEP rough ‐ in. Complete slab on grade and cure time. B3.5 to B3.7 ‐ Erect structural steel. Complete masonry walls. Complete roof (building to be watertight). B3.8 to B3.12 ‐ Complete interior CMU walls, metal studs. Complete in ‐ wall MEP rough ‐ ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough ‐ ins. B3.13 to B3.16 ‐ Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B3.17 to B3.20 ‐ Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B3.21 to B3.23 ‐ Complete fire alarm and security system. MEP start ‐ up.. Complete elevator inspection. B3.24 to B3.27 ‐ Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B3.28 to B3.30 ‐ Substantial completion, Final completion. Owner furniture, fixtures and equipment move ‐ in and occupy. S3.1 to S3.6 ‐ NTP,process shop dwgs/submittal/begin procurement Disconnect exist utilities to exist Fire Station. Install temp E&S/construction fence,protect communication tower, install staging area,construction S3.7 to S3.11 ‐ Demo existing fire station incl footings, foundations. Provide protection for cell town bldg. Fill void from basement. Route new utilities for tower. Inst. Stormwater basin and storm sewer piping. S3.12 to S3.15 ‐ Prepare bldg pad, inst. Undergrnd electric, gas to bldg. pad. Inst. San. Sewer/water piping and connect to street S3.16 to S3.18 ‐ Complete rough grading, inst. ret. walls, ext. light bases, post, lights. Inst. concrete curbs/sidewalks incl. work along Township Road. S3.19 to S3.21 ‐ Inst. stone base, base course paving for const. access including along Township Road. Inst. final pave and line striping. Complete final grading, seeding, landscaping. Issues Resolved Identified and located all utilities on site. Unsuitable soils removed and replaced with engineered fill to complete the building pad. Current Site Phase: Current Phase and Schedule Status

Pha

F M A M J

J A

Report Submission Date:

05/31/22

Report Author:

Colin Case

2023

Status Comments

F M ‐ A M ‐ J ‐ J A

‐ S O

‐ N D

% Complete

10% In progress: Building demolition completed

July 2022 thru July 2023

July 2022 thru September 2023

September 2022 thru November 2022

November 2022 thru January 2023

January 2023 thru March 2023

February 2023 thru April 2023

March 2023 thru May 2023

April 2023 thru July 2023

July 2023

ase Sitework 2022 ‐ 2023

Status Comments

S O N D J F M A

% Complete

100% Completed

Demolition, Temporary fencing, power, construction trailer and staging areas completed.

60%

10% Building pad construction underway.

Issues in Progress Scheduling all Cell Service providers to relocate all cell tower utilities.

Station #73

P a g e | 6 Northampton Township Fire Station #73 Project Number: 721001

2022

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J ‐ J A ‐ S O

Sitework Phasing (See Current Phase and Schedule Status) Building Phasing B73.1 to B73.4 ‐ Place foundations. Complete under slab MEP rough ‐ in. Complete slab on grade and cure time. B73.5 to B73.7 ‐ Erect structural steel. Complete exterior masonry walls. Complete roof (building to be watertight). B73.8 to B73.12 ‐ Complete interior CMU walls, metal studs. Complete in ‐ wall MEP rough ‐ ins. Complete overhead mechanical, plumbing, sprinkler, electric and data rough ‐ ins. B73.13 to B73.16 ‐ Install GWB walls and soffits. Complete painting. Energize permanent power. Install ceiling grid and set ceiling mounted devices. B73.17 to B73.20 ‐ Install casework. Install floor finishes in all areas except apparatus bays. Install vehicle exhaust system. Install floor finish apparatus bays. B73.21 to B73.24 ‐ Complete fire alarm and security system. MEP start ‐ up. Relocated offices from trailers to inside bldg. Complete elevator inspection. B73.25 to B73.28 ‐ Complete all final inspections. Complete final cleaning. Punchlist preparation and Contractor correction period. Owner training of all building systems. B73.29 to B73.31 ‐ Substantial completion, Final completion. Owner furniture, fixtures and equipment move ‐ in and occupy. S73.1 to S73.4 ‐ NTP,process shop dwgs/submittal/begin procurement. Disconnect exist utilities to exist Fire Station. Install temp E&S/construction fence, protect Verizon building. S73.5 to S73.9 ‐ Demo existing fire station incl footings, foundations and existing underground fuel oil tank. Install staging area, construction entrance, construction trailers, temporary, power, site lighting and communication from existing utilities. EC provide temporary overhead connections. Route new utilities for Verizon bldg. Install stormwater basin and connect to street and storm sewer piping to basin. S73.10 to S73.14 ‐ Prepare bldg. Pad, install underground electric and gas to bldg. Pad. Install sanitary piping. Sewer piping connect to street pipe. Complete rough grading, install retaining walls. S73.15 to S73.20 ‐ Remove construction trailers. Inst. ext. light bases, posts, lights. Inst. conc. curbs, stone base, base course paving for const. access. Inst. final paving and line striping. Complete final grading, seeding and landscaping. B73.1 to B73.4 ‐ Place foundations. Complete under slab MEP rough ‐ in. Complete slab on grade and cure time. Issues Resolved Unsuitable soils removed and replaced with engineered fill to complete the building pad. Current Site Phase: Current Building Phase: Current Phase and Schedule Status

F M A M J

Report Submission Date:

05/31/22

Report Author: Colin Case

2023

Status Comments

N ‐ D ‐ J F M ‐ A M ‐ J ‐ J A ‐ S O N ‐ D

% Complete

In progress: Building demolition and new building pad complete.

20%

5%

July 2022 thru July 2023

15% Foundation in progress.

September 2022 thru October 2022

November 2022 thru December 2022

January 2023 thru February 2023

February 2023 thru March 2023

March 2023 thru April 2023

April 2023 thru June 2023

June 2023 thru July 2023

Phase Sitework 2022 ‐ 2023

Status Comments

J A S O N D J F M A M J J

% Complete

100% Completed

100% Completed

Building pad Completed. Awaiting deliveries of storm structures and piping

20%

15% Foundation in progress.

Issues in Progress Actively addressing ground water during footing excavation.

Made with FlippingBook Ebook Creator