New Upper Dublin Middle School

March 2020

• The site has been cleared and soil stockpiled. • Storm water piping installation is ongoing. • Underground basin A1 is complete. • The contractor staging area is complete. • Temporary power lines to job trailers has been completed and inspected. • Set up of the temporary office trailers has competed. • The new domestic water meter pit has been approved and is being procured for installation during Spring Break.