New Lehigh Elementary School

Report Submission Date: April 2021

Report Author: M. Evans

2020

2021

Status Comments

% Complete

-D J-F M-A M-J J-A S-O N-D J-F M-A M-J J-A S-O N-D

Complete. Complete. Complete.

100% 100% 100%

Remaining work in later phasing. Parking lot utility work completed.

95%

100% 100%

Bus driveway base paving and curbing is completed. Finalized new parking and service areas. Secure site for school. Parking lot base tie-in complete. Landscaping behind curbs ongoing.

90% 40% 70% 40% 10% 75%

Relocation/removal of contractor storage boxes. Furniture order secured as of 1/28/21. Access road installation partially complete. Coordination of utility demo and abatement ongoing.

Phase is scheduled for May 2022

0% 0% 0%

Phases are scheduled for August 2022 Phases are scheduled for June - July 2022

Building foundation complete. Storm Tie-ins complete.

100% 100% 100%

Load bearing CMU complete.

Brick veneer complete. Curtain walls and CMP fascia's are ongoing.

Building enclosed. Roof detailing ongoing. MEP equipment installation ongoing.

98% 98% 90% 90% 40%

Punchlist remaining. Equipment commissioning verifcation ongoing.

Cleaners on-site, punchlist ongoing in classroom wing.

Furniture delivery 6/7/21.

2022

Status Comments

O N D J F M A M J

J A S S

% Complete

Detailing remaining on flat roof, curtain walls installed. Mechanical Systems are filled and factory start-up complete. Punchlist remaining. Cleaning and floor finishes ongoing. Paving to commence mid-June. Landscaping ongoing.

98% 98% 90% 80%

70% Coordination with PADOT for HOP work, finalized 21/22 Traffic patterns.

Start-ups and commissioning ongoing. Punchlist ongoing.

90%

Issues in Progress

Monitoring FFE budget with District. Water supply and septic removal from exisiting building and connection to new building is being coordinated. Coordination of abatement, utility removal and demolition of exisiting building with District move out schedule.

Paid to Date (with 10% retained)

Remaining Material Allowance

Executed Change Orders

Original Material Allowance

$ $ $ $ $ $

3,616,175 1,544,504 2,956,918 18,296,434

$ $ $ $ $ $

138,200

$ $ $ $ $ $

113,400 56,375 53,150 255,625

$ $ $ $ $ $

42,382 45,245 85,616 15,142 9,350 197,735

-

(148,314)

- -

-

9,350

26,414,031

(10,114)

487,900