New Lehigh Elementary School

Work in Progress - Building (CONT.)

• Energized the lighting circuit in the 1st floor classroomwing. •Continued the installation of lighting on the 2nd floor and in the Administration area. • Continued installation of interior aluminum curtain wall assemblies. • Began installation of flush wood doors in the Administration area. • Continued installation of casework and millwork in the corridors and Administration area. • Continued installation of Owner supplied items. • Began hanging acoustical sound panels in the classroomwing and library. • Began placement of epoxy terrazzo flooring in the Administration area and cafeteria.

Devices, lighting, wood doors, and signage are being installed in the classroomwing.

February 2021