NEW LEHIGH ELEMENTARY SCHOOL Northampton Area School District

DEI Project No.022034 Monthly Progress Report No.22 February 2021

Work In Progress

•Phase 2B: Interior and exterior finishes, MEP equipment installation and start-up, electrical systems and finishes. •Start: April 15, 2019 •Completion of Phase: June 15, 2021 Phase 2B: Site, 2BS.1-2BS.8 & Building, B1.5-B1.13.

• Continued installation of aluminum gutters and downspouts. • Continued painting of interior walls and door frames in the Administration area. • Completed the installation of the linear metal ceiling in the main lobby. • Installed ceilings in the kitchen and soffits in the cafeteria. • Completed the installation of hydronic and domestic water piping in the boiler room. • Made final connections to the boilers and pumps. Work in Progress - Building

Work in Progress - Building (CONT.)

• Energized the lighting circuit in the 1st floor classroomwing. •Continued the installation of lighting on the 2nd floor and in the Administration area. • Continued installation of interior aluminum curtain wall assemblies. • Began installation of flush wood doors in the Administration area. • Continued installation of casework and millwork in the corridors and Administration area. • Continued installation of Owner supplied items. • Began hanging acoustical sound panels in the classroomwing and library. • Began placement of epoxy terrazzo flooring in the Administration area and cafeteria.

Devices, lighting, wood doors, and signage are being installed in the classroomwing.

February 2021

Work in Progress

• Continued grading and spreading topsoil in areas around the building. • Began installation of concrete foundations for the playground pavilion. • Installed vehicle protection bollards around the propane tank farm. • Maintained E&S controls. Work In Progress - Site

Lighting and ceilings have been installed in the main lobby stair tower.

The elevator car has been installed and the shaft closed in.

Installation of epoxy terrazzo flooring at the main entrance.

The carpet in the library has been installed with the remaining millwork ongoing.

Acoustical sound panels for the STEAM classroom.

February 2021

Renderings

Building Layout First Level

Building Layout Second Level

February 2021

School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034

2019

Overall Project Schedule Status

J-F M-A M-J J-A S-O N-D

Site Milestones 1S.1 - 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT - 4/30 1S.3 - 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 - 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 - 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 - 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 - 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 - 2BS.8: Topsoil install, painting of lots and drives 3S.1 - 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 - 3S.7: Abatement, installation of access roads and parking lots 4S.1 - 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 - 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 - 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1-1B.3 - Prelim prep work, excavation & site, footings & foundations

1B.4 - Load bearing CMU 1B.5 - Exterior wall finishes

1B.6-1B.8 - Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9-1B.12 - Construction of interior walls, MEP rough-ins and equipment installation 1B.13-1B.16 - Interior & floor finishes, equipment start-up & commissioning, exterior finishes.

1B.17-1B.19 - Contractor cleanup and punchlist 1B.20-1B.21 - District cleanup, setup and move in

2020

2021

F M A M J J

Current Phase and Schedule Status - Site Phase 2B and Building Phase 1

1B.5-1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 1B.10-1B.12, 1B.15: MEP equipment piping and fixture installations 1B.13-1B.14: Ceiling and interior paint, floor finishes, wall coverings and displays installation 2BS.3-2BS.8: Construct fire lane, install curbing, sidewalk, new parking lot, begin landscaping 3S.6-3S.7: Finalize installation of bus/service access road and main parking area. 1B.15, 1B.17-1B.21: Equipment start-up and commissioning,clean-up and punchlist, set-up/move in

Issues Resolved Play Equipment order secured.

Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.

Contract Amount

$ $ $ $ $ $ $ $

5,499,330 1,157,573 29,289,026 4,080,000 1,663,000 118,026 3,341,000 20,087,000

Total Total Soft Costs: Current Remaining Project Contingency:

G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034 updated June 2020.xlsx

Report Submission Date: February 2021

Report Author: M. Evans

2020

2021

Status Comments

% Complete

D J-F M-A M-J J-A S-O N-D J-F M-A M-J J-A S-O N-D

Complete. Complete. Complete.

100% 100% 100%

Remaining work in later phasing. Parking lot utility work completed.

95%

100% 100%

Bus driveway base paving and curbing is completed. Finalized new parking and service areas. Secure site for school. Parking lot base tie-in complete. Landscaping behind curbs ongoing.

25% 10% 45% 25% 75%

Relocation/removal of contractor storage boxes. Furniture order secured as of 1/28/21. Access road installation partially complete. Phases are scheduled for Sept. 2021 through Jan. 2022

0% 0% 0% 0%

Phase is scheduled for May 2022

Phases are scheduled for August 2022 Phases are scheduled for June - July 2022

Building foundation complete. Storm Tie-ins complete.

100% 100% 100%

Load bearing CMU complete.

Brick veneer complete. Curtain walls and CMP fascia's are ongoing.

Building enclosed. Roof detailing ongoing. MEP equipment installation ongoing.

98% 90% 80% 80% 10% 95% 95% 85% 75% 50% 45%

Wall paint and floor finishes ongoing in Classroom wings.

Substantial Completion 5/27/21. Furniture order secured as of 1/28/21.

2022

Status Comments

A S O N D J F M A M J J

% Complete

Install and grade subbase, install base paving where available. Ceilings, flooring and casework ongoing in the Administration area. Exterior concrete paving. Installation of play area pavilion. Mechanical and domestic piping and equipment completed. Primary power installed. Start-ups and commissioning ongoing. Detailing remaining on flat roof, curtain walls installed.

Issues in Progress

Continuing to track FFE budget with District. Determining method of temporary water supply for commissioning and balancing.

Paid to Date (with 10% retained)

Remaining Material Allowance

Executed Change Orders

Original Material Allowance

$ $ $ $ $ $

3,420,949 1,477,018 2,884,783 17,087,491

$ $ $ $ $ $

138,200

$ $ $ $ $ $

113,400 56,375 53,150 255,625

$ $ $ $ $ $

54,268 46,093 85,616 51,819 9,350 247,145

-

(148,314)

- -

-

9,350

24,870,241

(10,114)

487,900

Aerial Shot

February 2021

Mr. Joseph S. Kovalchik, Superintendent Mr. Matthew Sawarynski, Business Administrator Mr. Jonathan Jenny, Director of Maintenance Mrs. Cassandra Herr, Principal

School Board David Gogel, President Charles Frantz, Vice President Dr. Michael Baird

John Becker James Chuss Charles Longacre Roy Maranki Robert Mentzell Ross Makary

Construction Manager D’Huy Engineering, Inc.

Project Architect KCBA Architects

Contractors Skepton Construction, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Cyprium Solutions, Inc. Electrical Construction

Myco Mechanical, Inc. Plumbing Construction

Made with FlippingBook - Online Brochure Maker