New Lehigh Elementary School - October 2020
Report Submission Date: October 2020
Report Author: M. Evans
2020
2021
Status Comments
% Complete
D J-F M-A M-J J-A S-O N-D J-F M-A M-J J-A S-O N-D
95% 100% 100% 95% 100% 100%
Parking lot utility work completed.
Bus driveway base paving and curbing is completed. Finalized new parking and service areas. Secure site for school. Parking lot base tie-in complete. Landscaping behind curbs ongoing.
75% 25%
0% 0% 0% 0% 0% 0% 0%
Phases are scheduled for Sept. 2021 through Jan. 2022
Phase is scheduled for May 2022
Phases are scheduled for August 2022 Phases are scheduled for June - July 2022
Building foundation complete. Storm Tie-ins complete.
100% 100%
Load bearing CMU complete.
Brick veneer complete. Curtain walls and CMP fascia's are ongoing.
85% 95% 85% 65% 70%
Building enclosed. Roof detailing ongoing. MEP equipment installation ongoing.
Wall paint and floor finishes ongoing in Classroom wings.
Substantial Completion 5/27/21.
0%
Status Comments
M A M J J A S O N D J F M
% Complete
Install and grade subbase, base paving where available. Ceilings, flooring and casework ongoing in the classroom wing. Exterior concrete paving and rough grading in parking area. Basement mechanical equipment piping is ongoing. Detailing remaining on flat roof, curtain walls installed.
95% 80% 75% 60% 20%
Issues in Progress
Finalizing wall graphic artwork, ordering material promptly will avoid delays for completion of interior finishes on specific walls.
Reviewing solutions to network connection in both New and existing building for Spring 2021.
Paid to Date (with 10% retained)
Remaining Material Allowance
Executed Change Orders
Original Material Allowance
$ $ $ $ $ $
2,913,301 1,374,684 2,605,874 15,759,275
$ $ $ $ $ $
(101,300)
$ $ $ $ $ $
113,400 56,375 53,150 255,625
$ $ $ $ $ $
89,756 43,536 88,337 51,819 9,350 282,798
- - - -
-
9,350
22,653,134
(101,300)
487,900