New Lehigh Elementary School - October 2020

School District: Northampton Area School District Project Name: New Lehigh Elementary School Project Number: 022034

2019

Overall Project Schedule Status

J-F M-A M-J J-A S-O N-D

Site Milestones 1S.1 - 1S.2: Notice to Proceed, Shop Drawings/Submittals NLT - 4/30 1S.3 - 1S.6: Install Construction Entrance, E&S Controls, Fencing, Staging Area, Demo of Powerlines 1S.7: Demolition of Residence 1S.8 - 1S.11: Installation of storm conveyance, start of new building construction 2AS.1 - 2AS.2: Relocation of fence, rough grading parking areas, underground utility installation 2AS.3 - 2AS.5: Parking area final grades and access areas, relocation of fence 2BS.1 - 2BS.5: Install fire lane, curbs, sidewalks and parking areas 2BS.6 - 2BS.8: Topsoil install, painting of lots and drives 3S.1 - 3S.3: Relocation of contractor staging area 3S.4: District to move out of existing building 3S.5 - 3S.7: Abatement, installation of access roads and parking lots 4S.1 - 4S.2: Existing building demolition 4S.3: Demolition of existing site improvements 5S.1 - 5S.2: Removal of staging area, fencing & existing site improvements 5S.3 - 5S.7: Finalize access roads, parking lots, landscaping, & athletic fields. Site final completion. Building Milestones 1B.1-1B.3 - Prelim prep work, excavation & site, footings & foundations

1B.4 - Load bearing CMU 1B.5 - Exterior wall finishes

1B.6-1B.8 - Roof structure and deck, roofing installation, permanent enclosure milestone 1B.9-1B.12 - Construction of interior walls, MEP rough-ins and equipment installation 1B.13-1B.16 - Interior & floor finishes, equipment start-up & commissioning, exterior finishes.

1B.17-1B.19 - Contractor cleanup and punchlist 1B.20-1B.21 - District cleanup, setup and move in

2020

2021

O N D J F M

1B.5-1B.8, 1B.16: Exterior wall finishes, roof structure and deck, permanent enclosure milestone 1B.10-1B.12, 1B.15: MEP equipment piping and fixture installations 1B.13-1B.14: Ceiling and interior paint, floor finishes, wall coverings and displays installation 2BS.3-2BS.8: Construct fire lane, install curbing, sidewalk, new parking lot, begin landscaping 3S.6-3S.7: Finalize installation of bus/service access road and main parking area. Current Phase and Schedule Status - Site Phase 2B and Building Phase 1

Issues Resolved

Contract Amount

Contract General Contractor: Skepton Construction, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Cyprium Solutions, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: Sargent Enterprises, Inc.

$ $ $ $ $ $ $ $

5,499,330 1,248,759 29,289,026 4,080,000 1,663,000 118,026 3,341,000 20,087,000

Total Total Soft Costs: Current Remaining Project Contingency:

G:\Projects\006-299 - Schools\022 - Northampton ASD\022034 Lehigh Elementary School\Payments & Change Orders\Contract Status and Payment Log_022034 updated June 2020.xlsx

Made with FlippingBook Learn more on our blog