New Fire Station #3 and New Fire Station #73 for Northampton Township
Report Submission Date:
05/06/22
Report Author: Colin Case
2023
Status Comments
M-A M-J J-A S-O N-D
% Complete
10% In progress: Building demolition completed
July 2022 thru July 2023
July 2022 thru August 2023
September 2022 thru October 2022
November 2022 thru December 2022
January 2023 thru February 2023
February 2023 thru March 2023
March 2023 thru April 2023
April 2023 thru June 2023
June 2023 thru July 2023
se Sitework 2022 - 2023
Status Comments
S O N D J F M A M J J
% Complete
100% Completed
Demolition, Temporary fencing, power, construction trailer and staging areas completed.
80%
Building pad construction underway.
Issues in Progress Unsuitable soils discovered below the existing building.
Remaining Material Allowance
aid to Date (with 10% retained)
Original Material Allowance
Executed Change Orders
822,753 155,934
$ $ $ $ $
- - - - -
$ $ $ $ $
612,400.00 88,540.00 131,682.40 76,465.00 909,087.40
$ $ $ $ $
612,400.00 95,540.00 131,682.40 76,465.00 916,087.40
-
91,832
1,070,518