New Central Emergency Services Facility
Projected Progress for Nov. 2021
• Complete duct insulation. • Complete overhead MEP rough-in in all building areas. • Continue interior block filler and painting. • Complete spray-foam insulation. • Begin installation of exterior brick veneer and stone. • Complete exterior framing and sheathing. • Begin setting mechanical VAV units. • Begin installation of windows. • Place concrete patio, metal pan stairs, and front and rear aprons. • Complete Plymavent System. • Begin installation of roof and exterior wall metal panels. • Continue interior framing and drywall installation. • Install apparatus bay doors.
Main electrical panel installation ongoing.
Exterior sheathing nearing completion.