New Central Emergency Services Facility -Upper Providence Township

Animated publication

Construction Manager

New Central Emergency Services Facility Upper Providence Township

DEI Project No.720001 Monthly Progress Report No.06 September 2021

New Central Emergency Services Facility

CURRENT MILESTONES DATES: Complete: P1.1 – P1.14, P1.17, P1.18 Complete underslab MEP installation (09/21/21)

Erect Structural Steel (09/30/21) Complete exterior walls (09/30/21) Ongoing: P1.15, P1.16, P1.19 – P1.23

Complete and cure Slab on Grade (10/13/21) Complete Roof – Roof Watertight (10/26/21) Complete interior walls (10/15/21) Complete MEP System Placement (12/15/21)

Site Construction Progress

• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete Belgian block and curb installation. • Complete base and binder courses on all asphalt paving except for the HOP connections. • Begin light pole base installation. Site Construction Progress

Building Construction Progress

• Complete under slab MEP installation. • Interior masonry wall installation and MEP in-wall rough-ins nearing completion. • Complete slab on grade and concrete mezzanine topping slab installation. • Complete steel erection and detailing. • Complete installation of metal roof decking.

• Exterior masonry wall installation nearing completion. • Continue mechanical hanger, duct, and pipe rough-in. • Begin exterior metal framing and sheathing. • Begin installation of sloped roof insulation and nail board. • Set mechanical roof top units.

y

Above ceiling MEP rough-in ongoing.

Exterior framing and sheathing ongoing.

September 2021

New Central Emergency Services Facility

Projected Progress for OCt. 2021

• Complete interior masonry wall installation and in-wall electrical rough-ins. • Complete exterior masonry wall installation. • Receive final steel inspection sign off. • Complete installation of sloped metal roof and 2-ply membrane flat roof.

• Complete mechanical duct and pipe hanger installation. • Continue overhead MEP rough-in in all building areas. • Begin interior painting. • Begin spray-foam insulation. • Begin installation of exterior brick veneer and stone. • Complete exterior framing and sheathing.

Concrete slab preparation completed in apparatus bay.

Base and binder paving courses complete.

y

Apparatus bay concrete slab complete.

Sloped roof insulation, nail board, and vapor barrier installation underway.

September 2021

Building Layout

Aerial view of building and material laydown area (September 2021).

Site Overview (September 2021).

Building Floor Plan

Building Site Plan

September 2021

Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001

20

Overall Project Schedule Status

J

F M A M J

Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals

P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP Commissioning P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping

P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion

Current Phase and Schedule Status

J F M A M J

P1.14 ‐ Complete under slab MEP piping and conduit P1.15 ‐ Complete Slab on Grade P1.16 ‐ Slab on Grade Curing Time P1.17 ‐ Erect Structural Steel P1.18 ‐ Complete Exterior Masonry Walls P1.19 ‐ Complete Roof ‐ Building to be Water Tight P1.20 ‐ Complete Interior Walls P1.21‐23 ‐ Complete Placement of MEP Systems

Issues Resolved Confirm installation detail and construction sequence of the apparatus bay trench drains. Coordinate with Lobar on roof nail board and stone veneer procurement. Coordinate the FF&E process with GKO and the Township. GKO confirmed building efficiency through a COMCheck stemming from perimeter insulation question.

Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.

Contract Amount

$ $ $ $ $

7,462,000 1,123,000 1,212,400

922,197

Total Total Soft Costs: Current Remaining Project Contingency

10,719,597

Other Discussion

Report Submission Date: September 2021

Report Author: Michael DePodwin

021

2022

J

A S O N

D J

F M A M J

% Complete

Status Comments

Resubmittals nearing completion

99%

Slab on Grade and Structural Steel complete. Exterior walls nearing completion. Roof & waterproofing ongoing. Interior block wall and MEP rough‐in ongoing

100% 80% 80%

0% 0% 0%

Fence to be completed

99%

Light base installation underway Complete Stabilization of site complete Base and binder paving courses complete.

75% 100%

25% 50%

0% 0%

Phase 1 2021

Status Comments

J A S O N D J F M A M J

% Complete

100% 100% 100%

Complete Complete Complete

Complete, awaiting final steel inspection sign off. Exterior walls nearing completion

99%

50% Sloped roof installation underway 95% 95% Interior walls nearing completion. 75% All system installation ongoing.

Issues in Progress

Complete a building low voltage, security, and access control design with GKO and CEI. Continue to monitor Erosion & Sedimentation Controls and respond to MCCD inspection report. Work with Vision Mechanical on resolving sprinkler shops drawings and calculations.

Ensure site hours, noise, and lighting are compliant with Township ordinances.

Paid to Date (with 10% retained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $

4,346,436

$ $ $ $ $

‐ ‐ ‐ ‐

$ $ $ $ $

209,365 47,807 94,098 37,920 389,190

$ $ $ $ $

184,489 47,807 104,631 64,622 401,549

356,591 360,850 399,003

5,462,879

1% Submittals

Requests for Information

0%

Approved Rejected Voided Overdue

0%

13%

Complete Outstanding Voided Overdue

0%

0%

86%

100%

Printed 10/20/2021

Tim Tieperman – Township Manager Bryan Bortnichak – Assistant Township Manager Dan Kerrigan – Chief of Fire And Emergency Services

Board of Supervisors Bill Starling – Chair Laurie Higgins – Vice Chair

Helene Calci John Pearson Albert Vagnozzi

Construction Manager D’huy Engineering, Inc.

Project Architect Gko Architects, Llc

Civil Engineer Gilmore & Associates, Inc.

Contractors Lobar, Inc. General Construction

Tri-County Mechanical, Inc. Mechanical Construction

Electri-Tech, Inc. Electrical Construction

Vision Mechanical, Inc. Plumbing Construction