New Central Emergency Services Facility -Upper Providence Township
New Central Emergency Services Facility
CURRENT MILESTONES DATES: Complete: P1.1 – P1.14, P1.17, P1.18 Complete underslab MEP installation (09/21/21)
Erect Structural Steel (09/30/21) Complete exterior walls (09/30/21) Ongoing: P1.15, P1.16, P1.19 – P1.23
Complete and cure Slab on Grade (10/13/21) Complete Roof – Roof Watertight (10/26/21) Complete interior walls (10/15/21) Complete MEP System Placement (12/15/21)
Site Construction Progress
• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete Belgian block and curb installation. • Complete base and binder courses on all asphalt paving except for the HOP connections. • Begin light pole base installation. Site Construction Progress
Building Construction Progress
• Complete under slab MEP installation. • Interior masonry wall installation and MEP in-wall rough-ins nearing completion. • Complete slab on grade and concrete mezzanine topping slab installation. • Complete steel erection and detailing. • Complete installation of metal roof decking.
• Exterior masonry wall installation nearing completion. • Continue mechanical hanger, duct, and pipe rough-in. • Begin exterior metal framing and sheathing. • Begin installation of sloped roof insulation and nail board. • Set mechanical roof top units.