New Central Emergency Services Facility - Upper Providence Township
New Central Emergency Services Facility
Projected Progress for May 2021
• Complete and have all Primes sign off on coordination drawings. • Complete installation of the sediment basin and rough grading. • Complete water line installation to building.
• Begin fiber optic duct bank installation. • Stabilize the southern half of the site. • Complete under slab MEP installation including the interior section of the radiant heat system. • Complete preparation of building pad to receive concrete slab on grade. • Begin placement of concrete slab on grade starting with the depressed slab at the Training O.A.C. Room and moving west to east. • Receive delivery of structural steel.
Sediment basin installation nearing completion.
Electrical duct bank to building complete.