New Central Emergency Services Facility - Upper Providence Township
Animated publication
Construction Manager
New Central Emergency Services Facility Upper Providence Township
DEI Project No.720001 Monthly Progress Report No.02 May 2021
New Central Emergency Services Facility
CURRENT MILESTONES DATES: Complete: P1.1 – P1.8, P1.12, P1.13 Complete building pad (05/28/21) Place building foundations (06/11/21) Ongoing: P1.8 – P1.11, P1.14 Install underground electric (05/04/21) Install underground water & sanitary (05/11/21)
Install underground gas (05/18/21) Complete under slab MEP (07/02/21)
Site Construction Progress Site Construction Progress
• Continue monitoring and maintaining site Erosion & Sedimentation controls. • Complete temporary electric to trailers. • Continue grading of site using the Township stockpile at the west end of the site. • Complete excavation and installation of storm structures at the sediment basin. • Continue site sewer and storm installation. • Begin installation of the water line from the meter pit to the building. • Begin underground electric duct bank installation.
Building Construction Progress
• Continue the BIM 3D modeling coordination drawing process. • Complete placement of concrete foundation walls and footings. • Complete masonry foundation walls and MEP foundation sleeves. • Complete foundation damp-proofing and insulation. • Complete structural backfilling of foundation walls. • Begin under slab MEP installation. • Begin preparing the building to receive concrete slab on grade.
y
Sediment basin outlet structures complete.
Exterior masonry foundation walls complete.
May 2021
New Central Emergency Services Facility
Projected Progress for May 2021
• Complete and have all Primes sign off on coordination drawings. • Complete installation of the sediment basin and rough grading. • Complete water line installation to building.
• Begin fiber optic duct bank installation. • Stabilize the southern half of the site. • Complete under slab MEP installation including the interior section of the radiant heat system. • Complete preparation of building pad to receive concrete slab on grade. • Begin placement of concrete slab on grade starting with the depressed slab at the Training O.A.C. Room and moving west to east. • Receive delivery of structural steel.
Sediment basin installation nearing completion.
Electrical duct bank to building complete.
y
Exterior foundation excavation, rebar and concrete placement.
Under slab plumbing installation ongoing.
May 2021
Building Layout
Aerial view of building foundations and material laydown area (May 2021).
Site Overview (May 2021).
May 2021
Owner: Upper Providence Township Project Name: New Emergency Services Facility Project Number: 720001
Overall Project Schedule Status
J
F M A M
Building Milestones P1.1‐P1.2 ‐ Notice to Proceed, Shop Drawings, Submittals
P1.12‐P1.17 ‐ Building Pad, Foundations, Structural Steel, Slab on Grade P1.18‐P1.19 ‐ Exterior Masonry walls, Waterproofing, Roof structure P1.20‐P1.24 ‐ Interior Partitions, MEP system placement
P1.25‐P1.33 ‐ Paint walls, Install Ceiling grids, Finishes, Casework, Flooring, Install Fire and Security Alarms, MEP C i i i P1.34‐P1.36 ‐ Final Inspections and Cleaning, Building Punchlist prep, Contractor correction period P1.37 ‐ P1.40 ‐ Owner Building Systems Training, Final Completion for New Building, Owner FFE and Move‐in Site Milestones P1.3‐P1.11 ‐ Temporary E&S, Install Staging, Construction Entrance and Fence, New Utilities installation P1.41 ‐ Installation of Site Lighting Bases and Lights P1.42 ‐ Curbing and Stone base for Parking Lots and Sidewalk installation P1.43‐P1.44 ‐ Installation of Sidewalks, Aprons and Site Concrete, Grading and Landscaping
P1.45‐P1.46 ‐ Final Grading and Site Signage, Paving P1.47‐P1.48 ‐ Demolish existing structure, Paving P1.54‐P1.55 ‐ Project Substantial and Final Completion
Current Phase and Schedule Status
J F M A M
P1.4 ‐ Establish temporary power, site lighting, and communications from existing utilities. P1.5 ‐ Install Temporary Electric for Construction Activities P1.6 ‐ Install basin and perform site rough grading
P1.7 ‐ Prepare building pad for foundations P1.8‐P1.11 ‐ Install MEP to building pad P1.12 ‐ Install building pad subgrade and complete building pad P1.13 ‐ Place building foundations P1.14 ‐ Complete under slab MEP piping and conduit
Issues Resolved Coordinate with PECO on energizing construction trailer temporary power pole. Confirm with Gilmore on new grading of merger pit and southwest corner of the sediment basin. Confirm new construction sequence and water pumping detail of the sediment basin proposed by Lobar, with Gilmore and MCCD.
Change construction detail of East Training O.A.C Room wall from decorative CMU to GWB on metal studs.
Contract General Contractor: Lobar, Inc. Mechanical Contractor: Tri‐County Mechanical, Inc. Electrical Contractor: Electri‐Tech, Inc. Plumbing Contractor: Vision Mechanical, Inc.
Contract Amount
$ $ $ $ $
7,462,000 1,123,000 1,212,400
922,197
Total Total Soft Costs: Current Remaining Project Contingency
10,719,597
Other Discussion
Report Submission Date: May 2021
Report Author: Michael DePodwin
2021
2022
J
J
A S O N
D J
F M A M J
% Complete
Status Comments
Foundations complete Resubmittals nearing completion
40% 0% 0% 0% 0% 0% 95%
Basin nearing completion, utilities underway
85%
0% 0% 0% 0% 0% 0%
Phase 1 2021
Status Comments
J J A S O N D J F M A M J
% Complete
95%
Lighting to occur once building pad underway
100% Complete
95%
Scheduled completion by 06/11/21
100% Complete 75% 100% Complete 100% Complete
Electrical duct bank complete, other utilities ongoing.
30% MEP underway working west to east
Issues in Progress
Continue to monitor Coordination Process. Coordinate new Day Room layout with Primes and GKO Continue tracking the submittal process. Continue to monitor Schedule. Continue to monitor Erosion & Sedimentation Controls.
Paid to Date (with 10% retained)
Original Material Allowance
Remaining Material Allowance 203,708 $ 47,807 $ 92,910 $ 64,622 $ 409,047 $
Executed Change Orders
$ $ $ $ $
1,681,900
$ $ $ $ $
‐ ‐ ‐ ‐
$ $ $ $ $
209,365 47,807 94,098 37,920 389,190
108,763 108,566 62,010
1,961,239
‐
0% Submittals
Requests for Information
0%
Approved Rejected Voided Overdue
2%
0%
0%
3%
Complete Outstanding Voided
98%
97%
Printed 6/14/2021
Tim Tieperman – Township Manager Bryan Bortnichak – Assistant Township Manager Dan Kerrigan – Chief of Fire And Emergency Services
Board of Supervisors Bill Starling – Chair Laurie Higgins – Vice Chair Hlene Calci John Pearson Albert Vagnozzi
Construction Manager D’huy Engineering, Inc.
Project Architect Gko Architects, Llc
Civil Engineer Gilmore & Associates, Inc.
Contractors Lobar, Inc. General Construction
Tri-County Mechanical, Inc. Mechanical Construction
Electri-Tech, Inc. Electrical Construction
Vision Mechanical, Inc. Plumbing Construction