New Central Emergency Services Facility - March & April Monthly Report

New Central Emergency Services Facility

Projected Progress for May 2021

• Design Team to complete review and approval of all remaining submittals and shop drawings. • Complete installation of basin and rough grading. • Complete exterior foundation excavation and concrete placement. • Continue installation of site sewer lines. • Begin installation of underground utilities to building pad. • Begin masonry and concrete foundation wall construction. • Begin layout, excavation, and placement of interior foundations. • Continue BIM 3D Modeling coordination process between all Primes.

Excavation and Structure Installation at Basin.

12” Ballast Stone for Staging Area.