New Central Emergency Services Facility - March & April Monthly Report
New Central Emergency Services Facility
Current Milestones Dates:
Complete: P1.1 – P1.7 Process Shop Drawings/Submittals (01/15/21) Prepare building pad for foundations (04/27/21) Ongoing: P1.8 – P1.13 Install underground electric (05/04/21) Install underground water & sanitary (05/11/21)
Install underground gas (05/18/21) Place building foundations (06/11/21)
Site Construction Progress Site Construction Progress
• Installed site fence and temporary erosion and sedimentation controls. • Performed tree, shrub, and vegetation removal. • Installed staging area and established construction entrance. • Set the temporary power pole and construction trailers. • Placed water meter pit off Golf Club Rd. • Began rough grading of site. • Began excavation of basin and installation of outlet structures and piping at basin • Began site sewer and storm structure installation. • The Design Team is continuing the shop drawing and submittal reviews. • The MC began the BIM 3D modeling coordination drawing process. • The GC issued the initial Critical Path Method Baseline Schedule to be utilized by all Primes. • Completed stone placement at building pad • Began foundation excavation, rebar placement, and concrete placement Building Construction Progress
Made with FlippingBook Ebook Creator