Lower Nazareth Elementary School
Animated publication
Construction Manager
Lower Nazareth Elementary School Nazareth Area School District
DEI Project No.017169 Monthly Progress Report No.04 January 2021
Work Completed
• Start: July 15, 2020 • Completion of Phase: April 2, 2021 Phase B1.1-B1.30: Building Phase 1
Work Completed
• Installation of steel bar joists in classroom addition area • Coordination drawings completed • Off site steel fabrication inspection • Steel decking and miscellaneous bridging • Perimeter CMU walls • Topping out exterior perimeter CMU walls • Roof drain procurement • Metal framing at Cafeteria • Steel decking of Administration addition
Metal Stud Framing at Cafeteria
Installation of Perimeter Wall Angle
Metal Stud Framing
January 2021
Work Ongoing
Above Ceiling Plumbing Venting
Roof Material Delivery
Installation of Ductwork
Shaft Wall Installation
Installation of CMUWalls
Under Slab Plumbing at Nurse’s Addition
January 2021
Work Ongoing
Work Completed
• Submittal processing • Steel wall angle bracing • Coordination for placement of roof curbs • Interior CMU non-bearing walls • Coordination with PPL for switch out of service with respect to new transformer location • Ongoing third-party inspections • Ongoing plumbing inspections • Ongoing electrical CMU wall rough-in • Ongoing MEP coordination of required wall openings in CMU walls • Interior door frame installations • Coordination and installation of roof drains • Coordination of pressure grouting sink hole area • Installation of feeder conduits towards new panels in Classroom addition • Coordination with switchgear change-out • Coordination with new transformer installation • Installation of above ceiling MEP work • Installation of Parapet wall steel plate and angle supports • Installation of underground plumbing to Nurses area, in old Stage room
• Installation of stone base for concrete slab in old Stage area • Roofing material delivery and coordination to commence
Parapet Plate Steel
Interior CMU
Interior Temporary Lighting
January 2021
Building Layout
Drone Photo of Administration Area
Drone Photo of Classroom Addition
January 2021
School District: Nazareth Area School District Project Name: Lower Nazareth Elementary School Additions & Renovations Project Number: 017169
2020
Overall Project Schedule Status
J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A
Site Phase 1 S1.1 ‐ S1.12 Temp E&S, const. entr.,utility disconnect,new water line,new ductbank,rem. grease trap,strip topsoil,inst. Basin & storm water syst.,prep building addition pad Bldg. Phase B1.1 ‐ B1.5 Bldg. protection, disconnect bldg. systems in spaces demolished, selective demo, inst. New utilities, new conc floor, add't foundation, CMU for slab install B1.6 ‐ B1.14 Under slab utilities, slab ‐ on ‐ grade, load bearing CMU, roof steel, interior CMU partitions, tie ‐ in roof B1.15 ‐ 1.22 ‐ Inst. MEP system equip & inspections, wall finishes and casework,ceiling grid,ceiling mounted devices/fixtures,inspections,inst. flooring B1.23 ‐ 1.30 ‐ Permanent power, equip. start ‐ up & commissioning mech. equip., equip. start ‐ up & commissioning elect., plumb, GC systems, move In B2.1 ‐ B2.14 ‐ Inter. Bldg. protection,select demo,inst. Add'n. Found/CMU, underslab elect,mech,plumbing,struct steel for add'n, conc. slab on grade, fire wall,ext. shell,int. walls,roof top equip,int. CMU walls B2.15 ‐ B2.25 ‐ Inst. rooftop equip, roof tie ‐ ins, rem. temp. partitions,above ceiling mech, elect, plumb and inspections,wall finish and casework,ceiling grid,ceiling mounted devices/fixtures and inspections,inst.flooring B2.26 ‐ B2.33 ‐ Rem. partition, equip. start ‐ up & commissioning of elect., plumb & GC systems, sub. comp. and move ‐ in to admin addition B3.1 ‐ B3.14 ‐ Abate caf and lobby,select demo, int. walls,roof top and above ceiling mech, elect, plumb systems and inspections, int. walls finish and casework, above ceiling mounted devices/fixtures and inspections,inst. flooring,sub. completion, final completion Site Phase 2.1 ‐ 2.7 Inst E&S, patch conc. Sidewalks, final grade & landscaping,rem const trailer/staging, inst. New basketball court
Buildin
Current Phase and Schedule Status
J A S O N D J F
B1.6 ‐ B1.14 Install underslab electrical, mechanical & plumbing syst. CMU framing for addition, roof steel, roof deck,concrete slab on grade
B2.1 ‐ B2.14: Installation of structural steel, Slab on Grade and CMU walls Coordinated placement of generator pad with district Sinkhole filled North Elevation, smaller sinkhole filled West Elevation Issues Resolved
Paid to
Contract Amount
Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: PRISM Response, LLC
$ $ $ $ $ $
4,422,000
$ $ $ $ $ $
939,000
1,287,597
42,082 456,001
Total
7,146,680
Report Submission Date:
01/31/21
Report Author: Lee Werkheiser
2021
2022
Status Comments
A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D
% Complete
100% Phase 1 site work has been completed
Phase 1 building demolition, CMU, Foundations, Concrete floor has been completed. Structural steel complete. Load bearing CMU wall installation is Complete. Roof decking is complete. Above Ceiling HVAC ducts installed. Above ceiling MC cable and junction boxes installed.
100%
97%
9%
0%
Phase 2 addition is ongoing, structural steel is complete, Demolition of existing stage is complete. Slab is placed at addition and at interior of old Stage area. Stud framing has commenced. Joist installation is planned.
50%
0%
0%
0%
0%
ng Phase 1 2021
Status Comments
M A M J J A S O N D
% Complete
Installation of door frames and interior CMU walls. 2 HR separation walls framed, Fire proofing completed on Door structural frame. Generator slab poured. Electrical panels installed Overhead MEP work commenced. Installation of protective barrier for demolition complete. Selective demolition of Stage and excavation. Prepared Building pad of addition. Completed Foundations and underslab MEP work. Erected structural steel. Poured Concrete slab. Framed stud wall at Cafeteria and sheetrocked.
97%
44%
Smaller sinkhole pressure grouting at West Elevation after snow melts Issues in Progress
o Date (with 10% retained)
Original Material Allowance
Remaining Material Allowance
Executed Change Orders
1,820,874
$ $ $ $ $ $
‐ ‐ ‐ ‐ ‐ ‐
$ $ $ $ $ $
2,934 42,270 515,354 70,490 43,280 356,380
$ $ $ $ $ $
356,380 43,280 55,960 42,270
222,702 208,806 298,822
2,273
2,934
2,553,477
500,824
Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr. Michael Santos, Principal
School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts
Construction Manager D’Huy Engineering, Inc.
Project Architect Alloy5 Architecture
Contractors CMG of Easton, Inc. General Construction
JBMMechanical, Inc. Mechanical Construction
Wind Gap Electric, Inc. Electrical Construction
JBMMechanical, Inc. Plumbing Construction