Lower Nazareth Elementary School

Animated publication

Construction Manager

Lower Nazareth Elementary School Nazareth Area School District

DEI Project No.017169 Monthly Progress Report No.04 January 2021

Work Completed

• Start: July 15, 2020 • Completion of Phase: April 2, 2021 Phase B1.1-B1.30: Building Phase 1

Work Completed

• Installation of steel bar joists in classroom addition area • Coordination drawings completed • Off site steel fabrication inspection • Steel decking and miscellaneous bridging • Perimeter CMU walls • Topping out exterior perimeter CMU walls • Roof drain procurement • Metal framing at Cafeteria • Steel decking of Administration addition

Metal Stud Framing at Cafeteria

Installation of Perimeter Wall Angle

Metal Stud Framing

January 2021

Work Ongoing

Above Ceiling Plumbing Venting

Roof Material Delivery

Installation of Ductwork

Shaft Wall Installation

Installation of CMUWalls

Under Slab Plumbing at Nurse’s Addition

January 2021

Work Ongoing

Work Completed

• Submittal processing • Steel wall angle bracing • Coordination for placement of roof curbs • Interior CMU non-bearing walls • Coordination with PPL for switch out of service with respect to new transformer location • Ongoing third-party inspections • Ongoing plumbing inspections • Ongoing electrical CMU wall rough-in • Ongoing MEP coordination of required wall openings in CMU walls • Interior door frame installations • Coordination and installation of roof drains • Coordination of pressure grouting sink hole area • Installation of feeder conduits towards new panels in Classroom addition • Coordination with switchgear change-out • Coordination with new transformer installation • Installation of above ceiling MEP work • Installation of Parapet wall steel plate and angle supports • Installation of underground plumbing to Nurses area, in old Stage room

• Installation of stone base for concrete slab in old Stage area • Roofing material delivery and coordination to commence

Parapet Plate Steel

Interior CMU

Interior Temporary Lighting

January 2021

Building Layout

Drone Photo of Administration Area

Drone Photo of Classroom Addition

January 2021

School District: Nazareth Area School District Project Name: Lower Nazareth Elementary School Additions & Renovations Project Number: 017169

2020

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A

Site Phase 1 S1.1 ‐ S1.12 Temp E&S, const. entr.,utility disconnect,new water line,new ductbank,rem. grease trap,strip topsoil,inst. Basin & storm water syst.,prep building addition pad Bldg. Phase B1.1 ‐ B1.5 Bldg. protection, disconnect bldg. systems in spaces demolished, selective demo, inst. New utilities, new conc floor, add't foundation, CMU for slab install B1.6 ‐ B1.14 Under slab utilities, slab ‐ on ‐ grade, load bearing CMU, roof steel, interior CMU partitions, tie ‐ in roof B1.15 ‐ 1.22 ‐ Inst. MEP system equip & inspections, wall finishes and casework,ceiling grid,ceiling mounted devices/fixtures,inspections,inst. flooring B1.23 ‐ 1.30 ‐ Permanent power, equip. start ‐ up & commissioning mech. equip., equip. start ‐ up & commissioning elect., plumb, GC systems, move In B2.1 ‐ B2.14 ‐ Inter. Bldg. protection,select demo,inst. Add'n. Found/CMU, underslab elect,mech,plumbing,struct steel for add'n, conc. slab on grade, fire wall,ext. shell,int. walls,roof top equip,int. CMU walls B2.15 ‐ B2.25 ‐ Inst. rooftop equip, roof tie ‐ ins, rem. temp. partitions,above ceiling mech, elect, plumb and inspections,wall finish and casework,ceiling grid,ceiling mounted devices/fixtures and inspections,inst.flooring B2.26 ‐ B2.33 ‐ Rem. partition, equip. start ‐ up & commissioning of elect., plumb & GC systems, sub. comp. and move ‐ in to admin addition B3.1 ‐ B3.14 ‐ Abate caf and lobby,select demo, int. walls,roof top and above ceiling mech, elect, plumb systems and inspections, int. walls finish and casework, above ceiling mounted devices/fixtures and inspections,inst. flooring,sub. completion, final completion Site Phase 2.1 ‐ 2.7 Inst E&S, patch conc. Sidewalks, final grade & landscaping,rem const trailer/staging, inst. New basketball court

Buildin

Current Phase and Schedule Status

J A S O N D J F

B1.6 ‐ B1.14 Install underslab electrical, mechanical & plumbing syst. CMU framing for addition, roof steel, roof deck,concrete slab on grade

B2.1 ‐ B2.14: Installation of structural steel, Slab on Grade and CMU walls Coordinated placement of generator pad with district Sinkhole filled North Elevation, smaller sinkhole filled West Elevation Issues Resolved

Paid to

Contract Amount

Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: PRISM Response, LLC

$ $ $ $ $ $

4,422,000

$ $ $ $ $ $

939,000

1,287,597

42,082 456,001

Total

7,146,680

Report Submission Date:

01/31/21

Report Author: Lee Werkheiser

2021

2022

Status Comments

A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

% Complete

100% Phase 1 site work has been completed

Phase 1 building demolition, CMU, Foundations, Concrete floor has been completed. Structural steel complete. Load bearing CMU wall installation is Complete. Roof decking is complete. Above Ceiling HVAC ducts installed. Above ceiling MC cable and junction boxes installed.

100%

97%

9%

0%

Phase 2 addition is ongoing, structural steel is complete, Demolition of existing stage is complete. Slab is placed at addition and at interior of old Stage area. Stud framing has commenced. Joist installation is planned.

50%

0%

0%

0%

0%

ng Phase 1 2021

Status Comments

M A M J J A S O N D

% Complete

Installation of door frames and interior CMU walls. 2 HR separation walls framed, Fire proofing completed on Door structural frame. Generator slab poured. Electrical panels installed Overhead MEP work commenced. Installation of protective barrier for demolition complete. Selective demolition of Stage and excavation. Prepared Building pad of addition. Completed Foundations and underslab MEP work. Erected structural steel. Poured Concrete slab. Framed stud wall at Cafeteria and sheetrocked.

97%

44%

Smaller sinkhole pressure grouting at West Elevation after snow melts Issues in Progress

o Date (with 10% retained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

1,820,874

$ $ $ $ $ $

‐ ‐ ‐ ‐ ‐ ‐

$ $ $ $ $ $

2,934 42,270 515,354 70,490 43,280 356,380

$ $ $ $ $ $

356,380 43,280 55,960 42,270

222,702 208,806 298,822

2,273

2,934

2,553,477

500,824

Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr. Michael Santos, Principal

School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts

Construction Manager D’Huy Engineering, Inc.

Project Architect Alloy5 Architecture

Contractors CMG of Easton, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Wind Gap Electric, Inc. Electrical Construction

JBMMechanical, Inc. Plumbing Construction

Made with FlippingBook Ebook Creator