Lower Nazareth Elementary School

Animated publication

Construction Manager

Lower Nazareth Elementary School Nazareth Area School District

DEI Project No.017169 Monthly Progress Report No.03 December 2020

Work Completed

• Start: July 15, 2020 • Completion of Phase: April 5, 2021 Phase B1.1-B1.30: Building Phase 1

Work Completed

• Exporting of fill • New opening in exterior wall at existing Stage area, for new door • Demolition of Stage area moveable partition • Demolition of Stage area HVAC ductwork • Demolition of Stage area lighting • Demolition of Stage area slab • Installation of CMU Steel Bearing walls • Sink Hole behind Classroom addition inspected by DBA and instructed to excavate, pour flowable fill, install Bentonite and backfill • Small Sink Hole was inspected by DBA, instructed to place flowable fill and suggested to pressure grout. • Coordinated slab placement for new location for existing generator • New Duct Bank excavated, conduits placed and concrete poured to

new Transformer location • Transformer Vault placed • Installation of steel beams in classroom addition • Installation of Steel bar joists in classroom addition area

• Coordination drawings completed • Off site Steel fabrication inspection

Excavation of old Stage

Completed Excavation of Sinkhole

Ductbank to New Transformer

Excavation of New Transformer Vault

HVAC RTU Delivery

December 2020

Work Ongoing

Work Ongoing

• Submittal processing • Steel Decking and miscellaneous bridging • Coordination for placement of roof curbs • Topping out exterior perimeter CMU walls • Interior CMU non-bearing walls • Coordination with PPL for switch out of service with respect to new Transformer location • Ongoing third-party inspections • Ongoing plumbing inspections • Ongoing Electrical CMUWall rough-in • Ongoing MEP coordination of required wall openings in CMU walls • Interior door frame installations

Installing Interior Classroom CMUWalls

CMU Exterior Wall Placement

Connector Corridor

Interior ClassroomWalls

December 2020

Work Ongoing

Installing Corridor Block

Setting Bar Joists

Ongoing Masonry Work

Setting Steel Joists

December 2020

Building Layout

December 2020

School District: Nazareth Area School District Project Name: Lower Nazareth Elementary School Additions & Renovations Project Number: 017169

2020

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M

Site Phase 1 S1.1 ‐ S1.12 Temp E&S, const. entr.,utility disconnect,new water line,new ductbank,rem. grease trap,strip topsoil,inst. Basin & storm water syst.,prep building addition pad Bldg. Phase B1.1 ‐ B1.5 Bldg protection, disconnect bldg systems in spaces demolished, selective demo, inst. New utilities, new conc floor, add't foundation, CMU for slab install B1.6 ‐ B1.14 Under slab utilities, slab ‐ on ‐ grade, load bearing CMU, roof steel, interior CMU partitions, tie ‐ in roof B1.15 ‐ 1.22 ‐ Inst. MEP system equip & inspections, wall finishes and casework,ceiling grid,ceiling mounted devices/fixtures,inspections,inst. flooring B1.23 ‐ 1.30 ‐ Permanent power, equip. start ‐ up & commissioning mech. equip., equip. start ‐ up & commissioning elect., plumb, GC systems, move In B2.1 ‐ B2.14 ‐ Inter. Bldg. protection,select demo,inst. Add'n. Found/CMU, underslab elect,mech,plumbing,struct steel for add'n, conc. slab on grade, fire wall,ext. shell,int. walls,roof top equip,int. CMU walls B2.15 ‐ B2.25 ‐ Inst. rooftop equip, roof tie ‐ ins, rem. temp. partitions,above ceiling mech, elect, plumb and inspections,wall finish and casework,ceiling grid,ceiling mounted devices/fixtures and inspections,inst.flooring B2.26 ‐ B2.33 ‐ Rem. partition, equip. start ‐ up & commissioning of elect., plumb & GC systems, sub. comp. and move ‐ in to admin addition B3.1 ‐ B3.14 ‐ Abate caf and lobby,select demo, int. walls,roof top and above ceiling mech, elect, plumb systems and inspections, int. walls finish and casework, above ceiling mounted devices/fixtures and inspections,inst. flooring,sub. completion, final completion Site Phase 2.1 ‐ 2.7 Inst E&S, patch conc. Sidewalks, final grade & landscaping,rem const trailer/staging, inst. New basketball court

Bui

Current Phase and Schedule Status

J A S O N D J

B1.6 ‐ B1.14 Install underslab electrical, mechanical & plumbing syst. CMU framing for addition, roof steel, roof deck,concrete slab on grade

B2.1 ‐ B2.14: Installation of strutural steel, Slab on Grade and CMU walls TV, Data, oulet and camera location coordination with District Sinkhole filled North Elevation, smaller sinkhole filled West Elevation Issues Resolved

Paid

Contract Amount

Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: JBM Mechanical, Inc.

$ $ $ $

4,422,000

$ $ $ $

939,000

1,287,597

456,001

Report Submission Date:

12/01/20

Report Author: Lee Werkheiser

2021

2022

Status Comments

M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

% Complete

100% Phase 1 site work has been completed

Phase 1 building demolition, CMU, Foundations, Concrete floor has been completed. Structural steel complete. Load bearing CMU wall installation is Complete. Roof decking is complete.

100%

66%

0%

0%

Phase 2 addition is ongoing, structural steel is complete, Demolition of existing stage is complete. Slab is placed at addition and at interior of old Stage area. Stud framing has commenced.

45%

0%

0%

0%

0%

ilding Phase 1 2020

Status Comments

F M A M J J A S O N D

% Complete

All underslab MEP work complete. CMU load bearing walls complete. Roof steel complete. Decking complete. Concrete slab complete. Installation of protective barrier for demolition complete. Selective demolition of Stage and excavation. Prepaired Building pad of addition. Completed Foundations and underslab MEP work. Erected structural steel. Poured Concrete slab. Framed stud wall at Cafeteria and sheetrocked.

97%

44%

smaller sinkhole pressure grouting at West Elevation Issues in Progress

Remaining Material Allowance

d to Date (with 10% retained)

Original Material Allowance

Executed Change Orders

1,430,514

$ $ $ $

‐ ‐ ‐ ‐

$ $ $ $

70,490 42,270 43,280 356,380

$ $ $ $

356,380 43,280 70,490 42,270

184,002 161,082 282,223

Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr.Michael Santos, Principal

School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts

Construction Manager D’Huy Engineering, Inc.

Project Architect Alloy5 Architecture

Contractors CMG of Easton, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Wind Gap Electric, Inc. Electrical Construction

JBMMechanical, Inc. Plumbing Construction

Made with FlippingBook - professional solution for displaying marketing and sales documents online