Lower Nazareth Elementary School
Work Completed
• Start: July 15, 2020 • Completion of Phase: April 5, 2021 Phase B1.1-B1.30: Building Phase 1
Work Completed
• Exporting of fill • New opening in exterior wall at existing Stage area, for new door • Demolition of Stage area moveable partition • Demolition of Stage area HVAC ductwork • Demolition of Stage area lighting • Demolition of Stage area slab • Installation of CMU Steel Bearing walls • Sink Hole behind Classroom addition inspected by DBA and instructed to excavate, pour flowable fill, install Bentonite and backfill • Small Sink Hole was inspected by DBA, instructed to place flowable fill and suggested to pressure grout. • Coordinated slab placement for new location for existing generator • New Duct Bank excavated, conduits placed and concrete poured to
new Transformer location • Transformer Vault placed • Installation of steel beams in classroom addition • Installation of Steel bar joists in classroom addition area
• Coordination drawings completed • Off site Steel fabrication inspection
Made with FlippingBook - professional solution for displaying marketing and sales documents online