Lower Nazareth Elementary School - February & March Monthly Report

Animated publication

Construction Manager

Lower Nazareth Elementary School Nazareth Area School District

DEI Project No.017169 Monthly Progress Report No. 5-6 February - March 2021

Work Completed - February

• Start: July 15, 2020 • Completion of Phase: April 2, 2021 Phase B1.1-B1.30: Building Phase 1

• Installation of above ceiling MEP work. • Installation of Parapet wall steel plate and angle supports. • 2 Hour fire wall framing and sheathing at Admin addition. • Classroom carrier installation in each classroom toilet room at Classroom addition. • Interior CMU non-bearing walls • Installation of roof drains and piping. • Installation of under slab plumbing at New Nurses area. • VAV and duct installation in Classroom addition. • New switch gear on site. • Installation of feeder conduits in Classroom addition. • Interior doorframe installation. Work Completed - February

2-Hour Wall Sheathing Installation

Above Ceiling MEP Rough-In

Above Ceiling MEP Rough-In

ClassroomWing Addition Roofing

CMU Installation at Administration Addition

Installation of Framed Parapet

Interior Framing Installation

MEP In-Wall Rough-In

February & March 2021

Work Ongoing - February

Work Ongoing - February

• Submittal processing. • Steel Wall angle bracing in Classroom addition. • Coordination and placement of roof curbs.

• Start installation of built-up roof insulation and roofing. • Interior framing of toilet rooms in Classroom addition. • Coordination with PPL for switch out of service with respect to new Transformer location. • Ongoing third-party inspections. • Ongoing plumbing inspections. • Ongoing Electrical CMUWall rough-in. • Coordination of Pressure grouting sink hole area. • Installation of feeder conduits towards new panels in Classroom addition. • Coordination with Switchgear change-out.

• Coordination with new transformer installation. • Roofing of Classroom addition and Admin addition.

VAV and Duct Installation

New Switch Gear on Site

Roof Curb Layout and Placements

Start Roof Install on Classroom Addition

February & March 2021

Work Completed - March

Work Completed - March

• Toilet roomwall framing in Classroom addition. • Interior CMU rubdown of walls in Classroom addition. • Installation of mechanical roof curbs. • Installation of built-up roof insulation and watertight at Classroom addition. • Interior CMU wall block prime and paint at Classroom addition. • Steel Wall angle bracing in Classroom addition. • Placement of mechanical roof curbs on Classroom addition. • Coordination of Pressure grouting sink hole area. • Installation of feeder conduits to new panels in Classroom addition. • Interior framing at each classroom entrance. • Framing of P-lam ceiling areas. • Installation of above ceiling circuits in Classroom addition. • Installation of tackboards and white boards in Classrooms of Classroom addition. • Installation of casework in Classroom addition. • Installation of concrete slab in old stage area and Admin addition. • Installation of ceiling grid in Classrooms of Classroom addition. • Installation of plumbing insulation, labeling and valve tagging in Classroom addition. • Topping out exterior perimeter CMU walls and steel plate installation on top of perimeter walls.

Coordination of Demolition in Work Room

East Elevation Classroom Addition Masonry

Parapet Wall Framing and Sheathing

February & March 2021

Work Ongoing - March

Work Completed - March

• Submittal processing. • Coordination with PPL for switch out of service with respect to new Transformer location.

• Ongoing third-party inspections. • Ongoing plumbing inspections. • Coordination with Switchgear change-out. • Coordination with new transformer installation. • Running dehumidifiers in Classroom addition. • Installation of above ceiling MEP work. • Installation of Brick veneer on Classroom addition. • Installation of CMU walls on Admin addition.

Plumbing and Mechanical Insulation

Plumbing Labeling and Tagging

Southeast Classroom Addition Elevation Masonry

Pressure Grouting

West Classroom Addition Elevation Ma- sonry

Toilet Rooms Framing

Wall Framing and Panel Prep

Whiteboard and Tackboard Installation

February & March 2021

Building Layout

Drone Photo of Administration Area

Drone Photo of Classroom Addition

February & March 2021

School District: Nazareth Area School District Project Name: Lower Nazareth Elementary School Additions & Renovations Project Number: 017169

2020

2

Overall Project Schedule Status

J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M

Site Phase 1 S1.1 ‐ S1.12 Temp E&S, const. entr.,utility disconnect,new water line,new ductbank,rem. grease trap,strip topsoil,inst. Basin & storm water syst.,prep building addition pad Bldg. Phase B1.1 ‐ B1.5 Bldg. protection, disconnect bldg. systems in spaces demolished, selective demo, inst. New utilities, new conc floor, add't foundation, CMU for slab install B1.6 ‐ B1.14 Under slab utilities, slab ‐ on ‐ grade, load bearing CMU, roof steel, interior CMU partitions, tie ‐ in roof B1.15 ‐ B1.22 ‐ Inst. MEP system equip & inspections, wall finishes and casework,ceiling grid,ceiling mounted devices/fixtures,inspections,inst. flooring B1.23 ‐ 1.30 ‐ Permanent power, equip. start ‐ up & commissioning mech. equip., equip. start ‐ up & commissioning elect., plumb, GC systems, move In B2.1 ‐ B2.14 ‐ Inter. Bldg. protection,select demo,inst. Add'n. Found/CMU, underslab elect,mech,plumbing,struct steel for add'n, conc. slab on grade, fire wall,ext. shell,int. walls,roof top equip,int. CMU walls B2.15 ‐ B2.25 ‐ Inst. rooftop equip, roof tie ‐ ins, rem. temp. partitions,above ceiling mech, elect, plumb and inspections,wall finish and casework,ceiling grid,ceiling mounted devices/fixtures and inspections,inst.flooring B2.26 ‐ B2.33 ‐ Rem. partition, equip. start ‐ up & commissioning of elect., plumb & GC systems, sub. comp. and move ‐ in to admin addition B3.1 ‐ B3.14 ‐ Abate caf and lobby,select demo, int. walls,roof top and above ceiling mech, elect, plumb systems and inspections, int. walls finish and casework, above ceiling mounted devices/fixtures and inspections,inst. flooring,sub. completion, final completion Site Phase 2.1 ‐ 2.7 Inst E&S, patch conc. Sidewalks, final grade & landscaping,rem const trailer/staging, inst. New basketball court

Building P

Current Phase and Schedule Status

J A S O N D J F M

B1.6 ‐ B1.14 Install underslab electrical, mechanical & plumbing syst. CMU framing for addition, roof steel, roof deck,concrete slab on grade B1.15 ‐ B1.22: MEP systems, finishes, Casework

B2.1 ‐ B2.14: Installation of structural steel, Slab on Grade and CMU walls

Issues Resolved Coordinated admin floor plan adjustments to leave existing fire alarm panel on existing wall portion.

Paid to Da ret

Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: PRISM Response, LLC

Contract Amount

$ $ $ $ $ $

4,422,000

$ $ $ $ $ $

939,000

1,287,597

456,001 42,082

Total

7,146,680

Report Submission Date:

03/31/21

Report Author: Lee Werkheiser

2021

2022

Status Comments

M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

% Complete

100% Phase 1 site work has been completed

100% Phase 1 building demolition, CMU, Foundations, Concrete floor has been completed. Structural steel complete. Load bearing CMU wall installation is Complete. Roof decking is complete. 97% Above Ceiling HVAC ducts installed. Above ceiling MC, FA, data cable and junction boxes installed. Casework in classrooms. Painted. Ceiling grid. 51%

0%

Phase 2 addition is ongoing, structural steel is complete, Demolition of existing stage is complete. Underslab plumbing is complete. Slab is placed at addition and at interior of old Stage area. Stud framing has commenced. Joist installation complete.

64%

0%

0%

0%

0%

Phase 1 2021

Status Comments

M A M J J A S O N D

% Complete

97% Installation of door frames and interior CMU walls. 2 HR separation walls framed, Fire proofing completed on Door structural frame. Generator slab poured. Electrical panels installed Overhead MEP work commenced. Completed exterior CMU walls. Installed Steel wall angle framing. Installed exterior door frame. Concrete foundation and slab complete. Fire walls complete. Metal frame parapet walls complete. 51% Roof top equipment placed, interior painting continuing, casework being placed

61%

Issues in Progress Smaller sinkhole pressure grouting at West Elevation after snow melts

ate (with 10% tained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $ $

316,308 53,746 42,088 38,639

2,229,436

$ $ $ $ $ $

‐ ‐ ‐ ‐ ‐ ‐

$ $ $ $ $ $

348,915 56,150 60,350 42,270

513,895 431,558 252,050

2,934

2,273

2,934

453,715

3,429,212

510,619

Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr. Michael Santos, Principal

School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts

Construction Manager D’Huy Engineering, Inc.

Project Architect Alloy5 Architecture

Contractors CMG of Easton, Inc. General Construction

JBMMechanical, Inc. Mechanical Construction

Wind Gap Electric, Inc. Electrical Construction

JBMMechanical, Inc. Plumbing Construction